31 USC 3554 - Sec. 3554. Decisions on protests

31 USC - US Code - Title 31: Money and Finance (January 2003)


Permanent Link: http://vlex.com/vid/19220517

Id. vLex: VLEX-19220517

Click here to download this article in graphic format (Acrobat Reader)

Search in this document

Sponsored Ads:


Text:

  (a)(1) To the maximum extent practicable, the Comptroller General shall provide for the inexpensive and expeditious resolution of protests under this subchapter.

Except as provided under paragraph (2) of this subsection, the Comptroller General shall issue a final decision concerning a protest within 100 days after the date the protest is submitted to the Comptroller General. (2) The Comptroller General shall, by regulation prescribed pursuant to section 3555 of this title, establish an express option for deciding those protests which the Comptroller General determines suitable for resolution within 65 days after the date the protest is submitted. (3) An amendment to a protest that adds a new ground of protest, if timely made, should be resolved, to the maximum extent practicable, within the time limit established under paragraph (1) of this subsection for final decision of the initial protest.

If an amended protest cannot be resolved within such time limit, the Comptroller General may resolve the amended protest through the express option under paragraph (2) of this subsection. (4) The Comptroller General may dismiss a protest that the Comptroller General determines is frivolous or which, on its face, does not state a valid basis for protest. (b)(1) With respect to a solicitation for a contract, or a proposed award or the award of a contract, protested under this subchapter, the Comptroller General may determine whether the solicitation, proposed award, or award complies with statute and regulation.

If the Comptroller General determines that the solicitation, proposed award, or award does not comply with a statute or regulation, the Comptroller General shall recommend that the Federal agency - (A) refrain from exercising any of its options under the contract; (B) recompete the contract immediately; (C) issue a new solicitation; (D) terminate the contract; (E) award a contract consistent with the requirements of such statute and regulation; (F) implement any combination of recommendations under clauses (A), (B), (C), (D), and (E); or (G) implement such other recommendations as the Comptroller General determines to be necessary in order to promote compliance with procurement statutes and regulations. (2) If the head of the procuring activity responsible for a contract makes a finding under section 3553(d)(3)(C)(i)(I) of this title, the Comptroller General shall make recommendations under this subsection without regard to any cost or disruption from terminating, recompeting, or reawarding the contract. (3) If the Federal agency fails to implement fully the recommendations of the Comptroller General under this subsection with respect to a solicitation for a contract or an award or proposed award of a contract within 60 days after receiving the recommendations, the head of the procuring activity responsible for that contract shall report such failure to the Comptroller General not later than 5 days after the end of such 60-day period. (c)(1) If the Comptroller General determines that a solicitation for a contract or a proposed award or the award of a contract does not comply with a statute or regulation, the Comptroller General may recommend that the Federal agency conducting the procurement pay to an appropriate interested party the costs of - (A) filing and pursuing the protest, including reasonable attorneys' fees and consultant and expert witness fees; and (B) bid and proposal preparation. (2) No party (other than a small business concern (within the meaning of section 3(a) of the Small Business Act)) may be paid, pursuant to a recommendation made under the authority of paragraph (1) - (A) costs for consultant and expert witness fees that exceed the highest rate of compensation for expert witnesses paid by the Federal Government; or (B) costs for attorneys' fees that exceed $150 per hour unless the agency determines, based on the recommendation of the Comptroller General on a case by case basis, that an increase in the cost of living or a special factor, such as the limited availability of qualified attorneys for the proceedings involved, justifies a higher fee. (3) If the Comptroller General recommends under paragraph (1) that a Federal agency pay costs to an interested party, the Federal agency shall - (A) pay the costs promptly; or (B) if the Federal agency does not make such payment, promptly report to the Comptroller General the reasons for the failure to follow the Comptroller General's recommendation. (4) If the Comptroller General recommends under paragraph (1) that a Federal agency pay costs to an interested party, the Federal agency and the interested party shall attempt to reach an agreement on the amount of the costs to be paid. If the Federal agency and the interested party are unable to agree on the amount to be paid, the Comptroller General may, upon the request of the interested party, recommend to the Federal agency the amount of the costs that the Federal agency should pay. (d) Each decision of the Comptroller General under this subchapter shall be signed by the Comptroller General or a designee for that purpose. A copy of the decision shall be made available to the interested parties, the head of the procuring activity responsible for the solicitation, proposed award, or award of the contract, and the senior procurement executive of the Federal agency involved. (e)(1) The Comptroller General shall report promptly to the Committee on Governmental Affairs and the Committee on Appropriations of the Senate and to the Committee on Government Reform and Oversight and the Committee on Appropriations of the House of Representatives any case in which a Federal agency fails to implement fully a recommendation of the Comptroller General under subsection (b) or (c). The report shall include - (A) a comprehensive review of the pertinent procurement, including the circumstances of the failure of the Federal agency to implement a recommendation of the Comptroller General; and (B) a recommendation regarding whether, in order to correct an inequity or to preserve the integrity of the procurement process, the Congress should consider - (i) private relief legislation; (ii) legislative rescission or cancellation of funds; (iii) further investigation by Congress; or (iv) other action. (2) Not later than January 31 of each year, the Comptroller General shall transmit to the Congress a report containing a summary of each instance in which a Federal agency did not fully implement a recommendation of the Comptroller General under subsection (b) or (c) during the preceding year. The report shall also describe each instance in which a final decision in a protest was not rendered within 100 days after the date the protest is submitted to the Comptroller General.


References In Text

Section 3(a) of the Small Business Act, referred to in subsec. (c)(2), is classified to section 632(a) of Title 15, Commerce and Trade.

Amendments

1996 - Subsec. (a)(1). Pub. L. 104-106, Sec. 5501(2)(A), substituted "100 days" for "125 days". Subsec. (b)(2). Pub. L. 104-106, Sec. 4321(d)(3), substituted "section 3553(d)(3)(C)(i)(I)" for "section 3553(d)(2)(A)(i)". Subsec. (e)(1). Pub. L. 104-106, Sec. 5501(2)(B)(i), substituted "Government Reform and Oversight" for "Government Operations". Subsec. (e)(2). Pub. L. 104-106, Sec. 5501(2)(B)(ii), substituted "100 days" for "125 days". 1994 - Subsec. (a)(1). Pub. L. 103-355, Sec. 1403(a)(1), substituted "125 days after" for "90 working days from". Subsec. (a)(2). Pub. L. 103-355, Sec. 1403(a)(2), substituted "65 days after" for "45 calendar days from". Subsec. (a)(3), (4). Pub. L. 103-355, Sec. 1403(a)(3), (4), added par. (3) and redesignated former par. (3) as (4). Subsec. (b)(3). Pub. L. 103-355, Sec. 1403(b)(1), added par. (3). Subsec. (c). Pub. L. 103-355, Sec. 1403(b)(2), amended subsec. (c) generally.

Prior to amendment, subsec. (c) read as follows: "(c)(1) If the Comptroller General determines that a solicitation for a contract or a proposed award or the award of a contract does not comply with a statute or regulation, the Comptroller General may declare an appropriate interested party to be entitled to the costs of - "(A) filing and pursuing the protest, including reasonable attorneys' fees; and "(B) bid and proposal preparation. "(2) Monetary awards to which a party is declared to be entitled under paragraph (1) of this subsection shall be paid promptly by the Federal agency concerned out of funds available to or for the use of the Federal agency for the procurement of property and services." Subsec. (e). Pub. L. 103-355, Sec. 1403(b)(3), amended subsec. (e) generally.

Prior to amendment, subsec. (e) read as follows: "(e)(1) The head of the procuring activity responsible for the solicitation, proposed award, or award of the contract shall report to the Comptroller General, if the Federal agency has not fully implemented those recommendations within 60 days of receipt of the Comptroller General's recommendations under subsection (b) of this section. "(2) Not later than January 31 of each year, the Comptroller General shall transmit to Congress a report describing each instance in which a Federal agency did not fully implement the Comptroller General's recommendations during the preceding fiscal year." 1988 - Subsec. (a)(1). Pub. L. 100-463 struck out "unless the Comptroller General determines and states in writing the reasons that the specific circumstances of the protest require a longer period" after "submitted to the Comptroller General" before period at end.

Change Of Name

Committee on Government Reform and Oversight of House of Representatives changed to Committee on Government Reform of House of Representatives by House Resolution No. 5, One Hundred Sixth Congress, Jan. 6, 1999.

Effective Date Of 1996 Amendment

For effective date and applicability of amendment by section 4321(d)(3) of Pub. L. 104-106, see section 4401 of Pub. L. 104-106, set out as a note under section 251 of Title 41, Public Contracts.

Amendment by section 5501(2) of Pub. L. 104-106 effective 180 days after Feb. 10, 1996, see section 5701 of Pub. L. 104-106, div. E, title LVII, Feb. 10, 1996, 110 Stat. 702.

EFFECTIVE DATE OF 1994 AMENDMENT

For effective date and applicability of amendment by Pub. L. 103-355, see section 10001 of Pub. L. 103-355, set out as a note under section 251 of Title 41, Public Contracts.

EFFECTIVE DATE Section applicable with respect to any protest filed after Jan. 14, 1985, see section 2751(b) of Pub. L. 98-369, set out as a note under section 251 of Title 41, Public Contracts.

PROMPT PAYMENT OF COSTS UNDER PRIOR LAW Section 1403(b)(4) of Pub. L. 103-355 provided that: "Costs to which the Comptroller General declared an interested party to be entitled under section 3554 of title 31, United States Code, as in effect immediately before the enactment of this Act [Oct. 13, 1994], shall, if not paid or otherwise satisfied by the Federal agency concerned before the date of the enactment of this Act, be paid promptly."

Section Referred To In Other Sections

This section is referred to in sections 3553, 3555, 3556 of this title; title 10 section 2305; title 22 section 3862; title 41 section 253b.

Other documents:
Peter J. Pryor, Petitioner-Appellant, v. Commissioner of Internal Revenue, Respondent-Appellee., 951 F.2d 1260 (10th Cir. 1991) | 7 CFR 1948.53 Definitions. | USA vs Easton 5th Cir 2001 | Resolucion de 12 de junio de 2003 de la Universidad de Oviedo por la que se publica el nombramiento de las comisiones que han de juzgar los concursos a Cuerpos Docente... | DECRETO 97/1990, de 3 de Abril, por el que se modifican determinados limit... | anuncios de audiencias tribunales juzgados y requisitorias | Información pública del estudio de detalle que acompaña el estudio de integración paisajística promovido por la en... | resolucion de 7 de enero de 2003 de la subsecretaria de promocion cultural por la que se deja sin efecto la ayuda concedida a diferentes galerias de ... | resolucion de 4 de marzo de 2008 de la direccion general de modernizacion de explotaciones y capacitacion agraria por la que declara la existencia de un foco de rhynchoph... | U. S. v. Carter, 582 F.2d 1280 (6th Cir. 1978)