4 CFR 21.10 - Express options, flexible alternative procedures, accelerated schedules, summary decisions, and status and other conferences.

Code of Federal Regulations - Title 4: Accounts (December 2005)


Permanent Link: http://vlex.com/vid/19599937

Id. vLex: VLEX-19599937

Click here to download this article in graphic format (Acrobat Reader)

Search in this document

Sponsored Ads:


Text:

TITLE 4 - ACCOUNTS

CHAPTER I - GOVERNMENT ACCOUNTABILITY OFFICE

SUBCHAPTER B - GENERAL PROCEDURES

PART 21 - BID PROTEST REGULATIONS

21.10 - Express options, flexible alternative procedures, accelerated schedules, summary decisions, and status and other conferences.

  (a) At the request of a party or on its own initiative, GAO may decide a protest using an express option.

  (b) The express option will be adopted at the discretion of GAO and only in those cases suitable for resolution within 65 days.

  (c) Requests for the express option shall be in writing and received in GAO not later than 5 days after the protest or supplemental/amended protest is filed. GAO will promptly notify the parties whether the case will be handled using the express option.

  (d) When the express option is used, the following schedule applies instead of those deadlines in 21.3 and 21.7: (1) The contracting agency shall file a complete report with GAO and the parties within 20 days after it receives notice from GAO that the express option will be used.

  (2) Comments on the agency report shall be filed with GAO and the other parties within 5 days after receipt of the report.

  (3) Where circumstances demonstrate that a case is no longer suitable for resolution using the express option, GAO shall establish a new schedule for submissions by the parties.

  (e) GAO, on its own initiative or upon request by the parties, may use flexible alternative procedures to promptly and fairly resolve a protest, including alternative dispute resolution, establishing an accelerated schedule, and/or issuing a summary decision.

  (f) GAO may conduct status and other conferences by telephone or in person with all parties participating in a protest to promote the expeditious development and resolution of the protest.

[61 FR 39042, July 26, 1996, as amended at 67 FR 79836, Dec. 31, 2002]

Other documents:
U.S v Armendariz 10th Cir 2008 | Duties of the Board of Directors When a Company Is for Sale | Joseph Patrick Thomas Doherty Petitioner-Appellant v Edwin Meese Attorney General of the United States ... | robert c harris appellant v dr r o settle warden medical center for federal prisoner... | RESOLUCION 61/2002 del Presidente del Consorcio para el Servicio de Extincion de Incendios y Salvamento de Navarra por la que se ... | CASE OF ROKHLINA v. RUSSIA | remisión de expediente al contencioso-administrativo | resolución de la dirección general del libro, archivos y bibliotecas, por la que se anuncia ... | Acordo do 12 de setembro de 2002, da Delegacion Provincial de Pontevedra, polo que se somete... | case of tribunal superior de justicia - bilbao, pais vasco - sala de lo social, of july 02, 2004 | Buckley v. Wintering (Ohio 2003) | RESOLUCION de 2 de noviembre de 2006, del Rectorado de la Universidad de Valladolid, por la que se aprueban l...