Alta Wind: Federal Circuit Reverses Trial Court And Kicks Case Back To Answer Primary Issue

On July 27, 2018, the US Court of Appeals for the Federal Circuit in Alta Wind v. United States, reversed and remanded what had been a resounding victory for renewable energy. The US Court of Federal Claims had ruled that the plaintiff was entitled to claim a Section 1603 cash grant on the total amount paid for wind energy assets, including the value of certain power purchase agreements (PPAs).

We have reported on the Alta Wind case several times in the past two years:

Government Appeal of Alta Wind Supports Decision to File Suit Now

Court Awards $206 Million to Alta Wind Projects in Section 1603 Grant Litigation; Smaller Award to Biomass Facility

Court Awards $206 Million to Alta Wind Projects in Section 1603 Grant Litigation; Smaller Award to Biomass Facility

Act Now To Preserve Your Section 1603 Grant

SOL and the 1603 Cash Grant - File Now or Forever Hold Your Peace

In reversing the trial court, the appellate court failed to answer the substantive question of whether a PPA that is part of the sale of a renewable energy facility is creditable for purposes of the Section 1603 cash grant.

Trial Court Decision

The Court of Federal Claims awarded the plaintiff damages of more than $206 million with respect to the cash grant under Section 1603 of the American Recovery and Reinvestment Act of 2009 (the Section 1603 Grant). The court held that the government had underpaid the plaintiff its Section 1603 Grants arising from the development and purchase of large wind facilities when it refused to include the value of certain PPAs in the plaintiffs' eligible basis for the cash grants. The trial court rejected the government's argument that the plaintiffs' basis was limited solely to development and construction costs. Instead, the court agreed with the plaintiffs that the arm's-length purchase price of the projects prior to their placed-in-service date informed the projects' creditable value. The court also determined that the PPAs specific to the wind facilities should not be treated as ineligible intangible property for purposes of the Section 1603 Grant. This meant that any value associated with the PPAs would be creditable for purposes of the Section 1603 Grant.

Federal Circuit Reverses and Remands

The government appealed its loss to the Federal Circuit. In its opinion, the Federal Circuit reversed the trial court's decision, and remanded the case back to the trial court with instructions. The Federal Circuit held that the purchase of the wind...