The Effective Use Of Experts And Expert Witnesses
Introduction
All construction projects are ultimately about using materials
and resources cost effectively to get something built. In achieving
those goals engineers and other construction professionals fulfill
a wide variety of roles providing technical expertise, project
management and contract administration. However, this will often
require them to become involved in disputes whether in respect of
certified sums, unpaid certificates, defective workmanship,
defective equipment, defective materials, or performance
shortfalls. In seeking to have those disputes resolved, engineers
and other construction specialists can and increasingly do play a
key role in the dispute resolution process.
In recent years, a growing range of preliminary dispute
resolution procedures have become available which are very
effective at screening out the vast majority of disputes. These are
principally adjudication, mediation, dispute boards and early
neutral evaluation. Many of these processes are consensual in
nature and none leads to a final and binding decision (unless the
parties agree).
However, there are three procedures which lead to final and
binding decisions by a third party: expert determination, court
litigation and arbitration. In the first procedure, it is the
expert who actually decides the outcome of the dispute. In the
latter two procedures, a third party (whether that be a judge or an
arbitration tribunal) will decide the outcome of the dispute based
upon the evidence before it, including consideration of any expert
opinion evidence provided by expert witnesses.
As engineers and other construction professionals participate in
these processes in two very different ways, this paper will seek to
identify the primary differences between those roles. It will
describe the role of an expert in the process of an expert
determination, and then consider the role of expert witnesses in
providing opinion evidence to assist a tribunal to reach its
decision (whether by way of litigation or arbitration).
Expert Determination
The term 'expert determination' describes a process
whereby the parties agree that a third party (the expert), who is
independent of the parties, is to be engaged to answer a particular
question or determine a particular dispute and that the parties are
to be bound by that expert's decision. The expert determination
process should, therefore, result in a fast, binding and final
resolution of the dispute referred to the expert.
The key distinguishing feature of expert determination is that
in general the expert is free to use his own knowledge, expertise
and experience to investigate the question that has been referred
to him, taking account of the submissions of the parties as he sees
fit, whereas judges and arbitrators are required to decide on the
basis of the submissions and evidence made by the parties. This is
one of the greatest strengths of expert determination, particularly
when the nature of the issue to be decided is technical, as the
expert will have been carefully selected because of his relevant
expertise. Therefore, the expert is not just appointed to hear the
parties' various contentions and to select between them, but to
investigate the facts and to apply his knowledge and expertise to
decide the answer to the question that has been referred to
him.
Expert determination is also very flexible. As it is based
entirely upon an agreement between the parties, they have an
opportunity to control and tailor the process to suit their own
particular circumstances or the facts and matters of the particular
dispute. This flexibility allows expert determination to be used in
a very broad range of matters, sometimes to avoid lengthy and
complex disputes from arising and at other times to resolve
disputes quickly and cheaply. It is not uncommon for parties to
agree that the whole process shall be concluded in a matter of days
after an expert has been appointed.
Having said that, the use of expert determination does carry
risks. The advantage of a final and binding decision carefully has
to be balanced against the risk of being unable to appeal or,
subject to only few very limited exceptions, to challenge the
expert's decision. The benefit of agreeing to a swift dispute
resolution process must also be weighed against the risk of the
procedure not allowing sufficient time for a full investigation
that other procedures might have allowed. Although experts must be
fair and impartial, they are not bound to observe due process or to
comply with the rules of natural justice. Since an expert is not
acting in a judicial capacity, the need for impartiality is also
more limited in scope when compared to judges and arbitrators, with
the result that an expert's decision will only be set aside if
actual bias is proved. This is illustrated in the recent case of
Owen Pell Limited v Bindi (London) Limited [2008] EWHC 1420
(TCC), where the parties agreed to have their dispute
determined by an independent expert. The defendant was unhappy with
the decision and refused to make payment contending that the expert
had not conducted himself in accordance with the principles of
natural justice, was biased or gave the appearance of bias, and
reached conclusions that were obviously in error or perverse. The
court reviewed the authorities and held that the expert's
decision was valid and enforceable, and that actual rather than
apparent bias was necessary to challenge an expert's
decision.
Types of dispute suitable for expert determination
Although parties may decide that any dispute arising out of a
project should be determined by an expert, it is more usual for the
parties to identify in their contract defined questions, issues or
subject areas about which a reference to an expert can be made.
Since one of the most significant benefits of expert determination
is that an appropriately qualified and respected expert will be
engaged to answer a question within his field of expertise, it can
easily be understood why this is the case. It may be relatively
easy for parties to agree, for example, that questions over whether
a complex piece of engineering equipment should be accepted as
complete could be resolved by an expert practising in the
particular field in question. However, it is quite another thing
for the parties to agree that every other potential dispute
including, for example, a dispute over the liability for and
consequences of delayed delivery should also be resolved by the
same individual.
For these reasons, expert determination is usually considered
most appropriate when narrow questions can be referred to an
appropriate expert be that an engineer, an accountant, a surveyor
or a lawyer. Some such issues can easily be identified at the time
that a contract is drafted. For example, it may be foreseeable that
there could be a dispute over whether a project had progressed to
the point where a completion certificate was due to an engineering
contractor, or over the appropriate price for a variation, or
deciding whether remedial work is required to engineering works, or
the appropriate accounting principles applicable to a valuation
exercise. By considering these issues pre-contract and by including
appropriate terms in the contract, both parties can enter into the
contract with the confidence of knowing that if certain disputes
arise they have the right to resolve those disputes through a
swift, relatively cheap and binding process, and that concerns over
lengthy and expensive litigation or arbitration can be put to one
side.
The Institution of Chemical Engineers (IChemE) has perhaps taken
the lead in developing a suite of standard term contracts where
expert determination is identified as a dispute resolution
procedure available to either party, and its experience suggests
that this has been very successful. Expert determination is
expressly identified as being available to the parties in respect
of disputes on subjects as diverse as objecting to a variation
order, disapproval by the project manager of documentation provided
by the contractor, whether a completion certificate or final
certificate should have been issued, the cost and time implications
of suspension orders and the amounts payable following termination.
The IChemE contracts provide that any dispute concerning one of
these identified subject areas shall be referred to expert
determination if one party serves notice to that effect on the
other. It also allows other issues to be resolved by expert
determination if both parties agree.
Agreements to refer issues to expert determination
Agreements that provide for an expert to answer a particular
question or to resolve disputes on particular issues vary widely in
their content and complexity. In the simplest of cases the parties
might merely agree, for example, that if they cannot agree on the
valuation of a particular property then the issue should be decided
by an independent chartered surveyor acting as an expert and not as
an arbitrator.
While such a simple agreement might be effective, experience
shows that it would leave many matters open to debate, so that some
of the benefits of expert determination could be lost. For these
reasons, it is common for parties to use one of the standard forms
to ensure that there is some certainty over the process and its
effectiveness.
The selection and appointment of an expert
Since the decision of the expert is to be final and binding, the
importance of the selection as to who to appoint or how that person
is to be selected cannot be overstated.
The courts do not have jurisdiction to select an expert for the
parties, so provision should be made naming the expert (and
possibly alternatives) in the contract or the contract should
provide reliable machinery for the selection and appointment of...
To continue reading
Request your trial