Federal Circuits, 10th Cir. (March 04, 1993)
Docket number: 91-6403
Permanent Link:
http://vlex.com/vid/ex-rel-rent-company-aetna-casualty-surety-37683501
Id. vLex: VLEX-37683501
Click here to download this article in graphic format (Acrobat Reader)

U.S. Court of Appeals for the 8th Cir. - Finch Equipment Corporation, D/B/a Finch Equipment Company, Appellee, v. Robert Frieden, D/B/a Frieden Construction Company, and Commercial Contractors of Nebraska, Inc., and Industrial Indemnity Company, Appellants., 901 F.2d 665 (8th Cir. 1990) D/B/a Finch Equipment Company, Appellee, v. Robert Frieden, D/B/a Frieden Construction Company, and Commercial Contractors of Nebraska, Inc., and Industrial Indemnity Company, Appellants.
U.S. Court of Appeals for the 10th Cir. - U.S. v. Kimberly Construction (10th Cir. 2002)
U.S. Court of Appeals for the 1st Cir. - Accusoft Corporation v. Palo (1st Cir. 2001)
U.S. Court of Appeals for the 1st Cir. - Keating v. Palo (1st Cir. 2001)
David W. Earman, Harrisonburg, VA, and Kelley L. Cornelius of Fogg, Fogg & Handley, Oklahoma City, OK, for plaintiff-appellant/cross-appellee.
John B. Hayes of Looney, Nichols, Johnson & Hayes, Oklahoma City, OK, for defendant-appellee/cross-appellant.Before McKAY, Chief Judge, LOGAN and SEYMOUR, Circuit Judges.McKAY, Chief Judge.After examining the briefs and appellate record, this panel has determined unanimously that oral argument would not materially assist the determination of this appeal. See Fed.R.App.P. 34(a); 10th Cir.R. 34.1.9. The case is therefore ordered submitted without oral argument.Plaintiff, Rent It Company, Inc., rented certain equipment to Sid's Eagle Enterprises for use in a U.S. Postal Service construction project in Edmond, Oklahoma. Sid's was a subcontractor with responsibility for steel erection on the project. As required by the Miller Act, 40 U.S.C. §§ 270a-d (1988), the project was covered by a payment bond, in this case provided by Defendant Aetna Casualty & Surety Company. Under the Miller Act, a "person who has furnished labor or material [to a federal project] ... and who has not been paid in full therefor [within] ninety days ... shall have the right to sue on [the] payment bond for the amount ... unpaid at the time of institution of such suit...." § 270b.Sid's experienced difficulties during the project and abandoned further work on it. At the time it abandoned the project, Sid's had not fully paid for the rental equipment it used. In addition, a Pittman Crane was returned by Sid's in damaged condition--its boom was bent and its tires were damaged. These were repaired by Plaintiff at its own expense after the equipment was returned. Plaintiff sought to recover both the unpaid rent and the cost of repairing the crane from the general contractor. When the parties could not agree on the amount owed, Plaintiff brought this action seeking to recover from Defendant's Miller Act bond.After a bench trial, the district court found Defendant liable for $3,147.97 in unpaid rent. In addition, it found that the damage to the crane resulted from the negligence of Sid's and concluded that, under the rental agreement, Sid's agreed to be liable for damage to the equipment resulting from negligent use. Because the trial court concluded that the Miller Act covered the repairs performed by Plaintiff, it found Defendant liable for the repair expenses, which it set at $12,536.08. However, it also ruled that Defendant was entitled to a set-off for $10,000 that Plaintiff had received from its own insurance carrier, reducing Plaintiff's damage award to $2,536.08. Finally, it concluded that Plaintiff could not recover its attorney's fees from Defendant, despite the presence of clauses to that effect in the rental agreement with Sid's. The district court concluded that the absence of privity of contract between Plaintiff and Defendant precluded enforcing the fee provisions against Defendant. In the alternative, it also ruled that awarding attorney's fees to Plaintiff would be inequitable, given that Plaintiff demanded over $26,000 and only won a judgment of $5,684.05.Plaintiff appeals the deduction of the $10,000 it received from its insurer and the denial of its motion for attorney's fees under the rental agreement. Defendant appeals from the award of repair costs to Plaintiff. We affirm in part and reverse in part.* This court set forth the rule in this circuit on recovering repair costs under the Miller Act almost fifty years ago in Continental Casualty Co. v. Clarence L. Boyd Co.,Try vLex for FREE for 3 days
Access legal information from United States including:
Try vLex without any commitment for 3 days and see why you need it.
3
days of Free Access