Nivani Ltd v China Jiangsu International (PNG) Ltd (2007) N3147
Jurisdiction | Papua New Guinea |
Judge | Lay J |
Judgment Date | 10 August 2007 |
Citation | (2007) N3147 |
Docket Number | WS 838 OF 2001 |
Court | National Court |
Year | 2007 |
Judgement Number | N3147 |
Full Title: WS 838 OF 2001; Nivani Ltd v China Jiangsu International (PNG) Ltd (2007) N3147
National Court: Lay J
Judgment Delivered: 10 August 2007
PAPUA NEW GUINEA
[IN THE NATIONAL COURT OF JUSTICE]
WS 838 OF 2001
BETWEEN
NIVANI LTD
Plaintiff
AND
CHINA JIANGSU INTERNATIONAL (PNG) LTD
Defendant
2007: 8 &18 May
10 August
CIVIL- construction contract - variation by conduct - conduct inconsistent with terms of written contract - intention of parties to be inferred.
CONTRACT - variation where no provision for variation - variation contract required.
REPUDIATION OF CONTRACT - contractor entitled to perform all works included in contract - termination of contract by employer before works complete is a repudiation.
DAMAGES - claim for delay caused by design change - claim for loss on repudiation of contract - claim for office overheads - all facts giving rise to calculation of claims must be proven.
Facts
The defendant was the principal contractor to the Waterboard for the construction of a building and an extension of a road. It sub-contracted the earthworks to the plaintiff for a lump sum not subject to alteration for variations in quantities. The sub-contract was a written agreement annexing drawings and specifications for the work. Shortly after the work commenced the defendant provided the plaintiff with revised drawings which, amongst other things, increased some of the earthworks. The defendant claimed payment on a rate for work done basis and was paid on the basis. Some six weeks after the contract commenced the defendant provided the plaintiff with further drawings and invited the plaintiff to provide a price for the work in those drawings which included thickening and widening the pavement, curb and channel, concrete footpath and bitumen sealing. The defendant did not accept the plaintiff's price and later performed this work itself and by others. The works being performed by the plaintiff were suspended when they were nearing completion and 11 months later the defendant informed the plaintiff that the sub contract was terminated. The plaintiff claimed damages, for unpaid completed work, for delay in the initial works because of the design change, for being prevented from completing the work contracted, and for office overheads during the period of suspension of the work. Some of the facts necessary for a proper calculation of damages were not proven.
Held
1. Parties may by agreement, vary a contract made by them;
2. where a contract makes no provision for variation there must be a contract of variation to bind the parties;
3. a contract of variation can be formed by the conduct of the parties;
4. a contractor is entitled to perform all of the works contained in his contract but is not entitled to perform any new and additional works which the employer may decide upon, except by agreement;
5. all of the facts necessary to establish a claim for damages must be proven;
6. a claim for loss of profit or overheads must include proof of the actual percentage of profit or overhead applicable to the contractor as a percentage of gross turnover;
7. the facts established that the lump sum contract was amended by the conduct of the parties to be a contract to be paid by rates against measured work;
8. the contract included work which had not been completed when the works were suspended and subsequently the contract was terminated by the defendant. Consequently the defendant repudiated the contract.
9. The claim for work done but not paid for was not proven. The other heads of damage were only partially proven.
10. The court can make an award of damages where the evidence establishes that a loss has been sustained but the evidence is inadequate to calculate a specific figure.
Cases Cited
PNG Cases
National Housing Commission v Queensland Insurance (PNG) Pty Ltd [1988-89] PNGLR 474
Curtain Brothers v The State [1993] PNGLR 285
Yange Langan v Independent State of Papua New Guinea, (1999)N 1369
Overseas Cases Cited
Thorn v London Corporation (1876) 1 App. Cas. 120
Gallagher v Hirsch (1899) NY45 App. Div. 467
Morris v Barron and Company [1918] AC 1
Sunney v Cunard White Star [1940] 1 KB 740
Carr v J. A. Berryman Pty Ltd (1953) 27 ALJ 273
British and Bennington Ltd v NW Cocher Tea Co & Ors [1923] AC 48
Chittick & Tailor (1954) 12 WWR 653 (Canada) 655
Shore v Horwitz [1964] SCR 588 (Canada)
United Dominion Corporation (Jamaica) Ltd v Shocar [1969] AC 340
Jones v Schiffman (1971) 124 CLR 303
Commonwealth v Crothall Hospital Services (Australia) Ltd (1981) 54 FLR 439
Tallerand Co. Pty. Ltd v Nathans Merchandise (Victoria) Pty. Ltd [1957]
Dai v Barclay Brothers Australia (1983) 57 ALJR 442
Integrated Computer Services Pty Ltd v Digital Equipment Corp., (Australia) Pty Ltd (1988) 5 BPR 11 110
HCA 10; 98 CLR 144
The Commonwealth v Amann Aviation Pty Ltd (1991) 174 CLR 64
Commissioner of Taxation V Sara Lee Household and Body Products (2000) 201 CLR 520
Brambles Holdings Ltd v Bathurst City Council (2001) 53 NSWLR 153
Eldridge Pty Ltd v BGC Construction Pty Ltd [2006] WASCA 264
References
Judicial Proceedings (Interest on Debts and Damages) Act
Hudson's Building and Engineering Contracts, 10th edition by L. N. Wallace
Counsel
D. Lidgett, for the Plaintiff
J. Latu, for the Respondent
10 August, 2007
1 LAY J.:
2 A few days after China Jiangsu asked Nivani to commence the works under the sub contract, China Jiangsu gave Nivani revised drawings for the work, which had been given to it by its principal.
3 Nivani's case is that the whole basis of the contract was altered by the revised drawings provided at the end of March. Nivani, by letter dated 3 April 2000, told China Jiangsu that Nivani would have to use a different construction method, and that it would cost more. Nivani proceeded to construct the works in accordance with the new drawings, the work done was measured in accordance with the letter sent by Nivani to China Jiangsu, and an interim payment made based on rates provided by Nivani. This payment included quantities never contemplated in the original contract. In late April 2000, a further set of amended drawings making substantial changes to the works was given to Nivani by China Jiangsu. Part of the original works were completed by the 30th of April 2000. Works were suspended on the road to permit laying of drains by others and Nivani never received notice to resume the work. In March 2001, it received notice that the contract was terminated. It therefore lost amongst other things, the profit it would have earned for the balance of the contract.
4 China Jiangsu, has argued that the contract was never varied, Nivani carried out all of the works required of it under the original sub contract agreement, those works were measured, agreed and paid for. Nivani submitted a price for the varied works but that price was never accepted. It argues Nivani has no claim.
5 It is necessary therefore for me to identify what were the terms of the contract between Nivani and China Jiangsu under which Nivani carried out the work, whether China Jiangsu is in breach of that contract and whether any sum is due to Nivani under the contract or in damages.
6 The first observation I make is that the main contention by China Jiangsu set out above cannot be right. The term of the written sub contract, that there would be no variation in price for variation in quantity of earthworks, cannot operate only to fix the price against Nivani. It must also operate to fix the price against China Jiangsu. There was no provision in the signed sub contract for payment by measurement of the works. That is, if as China Jiangsu claims, there was no variation and Nivani performed all of the work required of it under the signed sub contract, then Nivani must be entitled to the agreed contract price of K95,968.62 excluding VAT. Of that total amount K75,319.23 related to the Adima Street extension works. China Jiangsu on its own submissions only paid Nivani K 64,738.60, for all the works for the Adima Street extension. Therefore, if I accept China Jiangsu's contention that there was no variation to the original sub contract agreement, there must be due to Nivani the sum of K 10,580.63 being the balance of the agreed price for the sub contract. This I consider must follow from what I have said and from submission of counsel for China Jiangsu in which he said "... the price was...
To continue reading
Request your trial-
NATIONAL CAPITAL DISTRICT WATER & SEWERAGE LIMITED trading as EDA RANU v YAMBARAN PAUSA SAKA BEN LIMITED
...Tuna Cannery [2000] PNGLR 213 National Broadcasting Corporation v Taison (2019) N8083 Nivani Ltd v China Jiangsu International (PNG) Ltd (2007) N3147 Papua Club Inc v Nusaum Holdings Ltd (2005) SC812 Papua New Guinea Banking Corporation v Tole (2002) SC694 PNG Ports Corporation Ltd v Canopu......
-
Raikos Holdings Ltd v G & S Ltd
...[2000] PNGLR 213 Niugini Civil & Petroleum Ltd v WNB Development Corporation Ltd (2005) N2909 Nivani Ltd v China Jiangsu International Ltd (2007) N3147 Pama Anio v Aho Baliki (2004) N2719 Peter Aigilo v The State (2001) N2102 ORIGINATING SUMMONS The plaintiff sought a declaration that it la......
-
Reko PNG Ltd v Gopera Investment Ltd
...N3649 Con v. Jant Ltd (2014) N5503 Kurumbakari Ltd v. ENFI (PNG) Co Ltd (2012) N4704 Nivani Ltd v. China Jiangsu International (PNG) Ltd (2007) N3147 Raikos Holdings Ltd v. G & S Ltd (2014) N5613 Vanimo Forest Products Ltd v. Ossima Resources Ltd (2013) SC1275 Overseas Cases British and Ben......
-
Timothy Con v Jant Limited (2014) N5503
...Bio-Normalizer (PNG) Ltd v CPL (2009) N3649 Kurumbukari Ltd v Enfi (PNG) Ltd (2012) N4704 Nivani Ltd v China Jiangsu International Ltd (2007) N3147 STATEMENT OF CLAIM These were proceedings in which the plaintiff sought to establish liability in damages for breach of a contract of employmen......
-
NATIONAL CAPITAL DISTRICT WATER & SEWERAGE LIMITED trading as EDA RANU v YAMBARAN PAUSA SAKA BEN LIMITED
...Tuna Cannery [2000] PNGLR 213 National Broadcasting Corporation v Taison (2019) N8083 Nivani Ltd v China Jiangsu International (PNG) Ltd (2007) N3147 Papua Club Inc v Nusaum Holdings Ltd (2005) SC812 Papua New Guinea Banking Corporation v Tole (2002) SC694 PNG Ports Corporation Ltd v Canopu......
-
Raikos Holdings Ltd v G & S Ltd
...[2000] PNGLR 213 Niugini Civil & Petroleum Ltd v WNB Development Corporation Ltd (2005) N2909 Nivani Ltd v China Jiangsu International Ltd (2007) N3147 Pama Anio v Aho Baliki (2004) N2719 Peter Aigilo v The State (2001) N2102 ORIGINATING SUMMONS The plaintiff sought a declaration that it la......
-
Reko PNG Ltd v Gopera Investment Ltd
...N3649 Con v. Jant Ltd (2014) N5503 Kurumbakari Ltd v. ENFI (PNG) Co Ltd (2012) N4704 Nivani Ltd v. China Jiangsu International (PNG) Ltd (2007) N3147 Raikos Holdings Ltd v. G & S Ltd (2014) N5613 Vanimo Forest Products Ltd v. Ossima Resources Ltd (2013) SC1275 Overseas Cases British and Ben......
-
Timothy Con v Jant Limited (2014) N5503
...Bio-Normalizer (PNG) Ltd v CPL (2009) N3649 Kurumbukari Ltd v Enfi (PNG) Ltd (2012) N4704 Nivani Ltd v China Jiangsu International Ltd (2007) N3147 STATEMENT OF CLAIM These were proceedings in which the plaintiff sought to establish liability in damages for breach of a contract of employmen......