Consortium Commercial Developments Ltd V ABB Ltd

Previous Real Estate Bulletin articles have considered terminal dilapidations and the considerable importance of both landlords and tenants making their cases on liability and quantum clear at an early stage of any dispute in order to comply with the Dilapidations Protocol. The recent case of Consortium Commercial Developments Ltd v ABB Ltd [2015] EWHC 2128 (TCC) is an example of the court's flexible approach to analysing the expert valuation evidence should a dispute ultimately proceed to a trial and of the effect this may have on any eventual liability of the former tenant for terminal dilapidations.

Facts of the case

In 1996 Consortium Commercial Developments ("Consortium") granted a lease to ABB which came to an end in June 2011. The premises were a B1 hybrid unit located on a business park in Milton Keynes. Four years later, the disrepair existing at the expiry of the lease and failure to re-instate the premises had not been remedied. Consortium's position was that it did not want to fund the costs of the works without first recovering those costs from ABB. Consortium also wished to await an improvement in market conditions, before incurring the costs of the works and re-letting the unit. Therefore Consortium made a claim for dilapidations against ABB. Consortium's claim was limited by s.18 of the Landlord and Tenant Act 1927 to damages amounting to the diminution in value of the premises caused by the disrepair at the end of the lease.

The claims

By the time the case came to trial, surveyors instructed by the parties had agreed that the costs of reinstatement and remedying the disrepair under the lease totalled GBP 315,258.77 and that the necessary works would take 12 weeks. Consortium also claimed for loss of rent and rates over this 12 week period. This claim was based on the previous passing rent of GBP 160,000 pa and rates of GBP 728.60 pw, resulting in a further claim for GBP 45,666.24.

ABB had previously sublet the property in 2003 and, upon vacation, the sub-tenant had paid GBP 160,000 to ABB in respect of its terminal dilapidations liabilities. ABB had then made attempts to re-let the premises in its unrepaired condition with no success. ABB had refused to pay any amount to Consortium for dilapidations (not even the GBP 160,000) and Consortium therefore claimed 6% pa interest (a higher interest rate than the norm), as a means of penalising ABB for not accounting for this recovery, or any dilapidations, to Consortium.

Expert...