Demolition Works: Some Contractual Issues
The legal issues arising out of the contractual provisions for
demolition works are not quite as simple as might first be
apparent. First, the form of contract needs to be chosen: two
principal proprietary forms of contract are available, as
follows:-
NFDC: National Federation of Demolition
Contractors Form of Direct Contract 2000 is demolition-specific and
designed to cover all aspects of demolition works (rather than
standard construction works), but unsurprisingly is fairly
demolition contractor 'friendly' (in respect of risk
allocation);
JCT: though the JCT Minor Works Construction
Contract 2007 does not cater specifically for demolition
activities, it is relatively straightforward and less biased (than
the NFDC form) towards the contractor.
A prudent employer will probably wish to amend one or other of
these contract forms either to make them less contractor
'friendly' and/or to make them demolition industry
specific.
However, where demolition works are being carried out prior to
main building works under a more complex transaction (such as an
NHS LIFT, BSF or PFI project), which involves a wider range of
interested parties (including perhaps a local authority or NHS
primary care trust), more complex contractual arrangements may be
necessary or at least unavoidable. In such circumstances the
demolition arrangements are typically structured in one of two
ways:-
back-to-back contracts: under a head-contract
with the public authority, the private sector partner (SPV)
undertakes to carry out the demolition works, but simultaneously
enters into a contract on broadly identical terms to flow-down its
obligations to a specialist demolition contractor. Such 'back
to back' arrangements are designed to ensure that: (a) the SPV
can flow-up appropriate obligations (such as payment for the works
and undertakings not to put the SPV in breach of its obligations
under the demolition contract) to the public authority; and (b) the
public authority can flow-down appropriate obligations (such as
covenants relating to the use of the land) to the SPV.
Derogations from the market norm allocations of risks and
obligations would need to be negotiated on a project-specific
basis. The risk of insolvency or other default by the demolition
contractor is likely to be of particular interest to the other
parties;
licence for works: alternatively, the public
authority might grant to the SPV a licence to carry out the
demolition works, authorising the SPV to enter into...
To continue reading
Request your trial