PFI/PPP Disputes - Part 1
Foreword
It is now over 13 years since the first public finance
initiative/public private partnership ("PFI/PPP")
projects were completed in the UK and there were, as at the end of
2008, some 935 PFI/PPP projects worth over £66 billion. The
number of projects and the time over which they have been operating
enable some assessment to be made of where problems are emerging or
are likely to emerge and what the nature of those problems is
likely to be.
The market has changed between 2008 and 2009 as the UK and
global economies have declined. The "credit crunch",
i.e. the sharp reduction in bank lending as a result of
banks' substantial losses, has had the obvious effect on PFI
projects of a decline in bank lending to the private sector. This
has led to the government in the UK providing funding for projects
for which private finance is no longer available, so that,
paradoxically, "private finance initiative" projects may
proceed without or with reduced private finance. There has also
been a reduction in new PFI/PPP projects. Nevertheless, there still
exists a substantial PFI/PPP market in the UK.
In a typical PFI/PPP project, the head contract is an agreement
between an organ of government ("the Authority") and a
consortium whose task it is to design, build and operate the
project. This consortium will typically consist of a funder, a
construction company and a facilities management company, often in
the form of a limited company special purpose vehicle formed solely
for the purpose of the project ("SPV"). The SPV will
itself have a contract regulating the relationship between its
members (a shareholders' agreement). The SPV will enter into
various sub-contracts for the performance of the project, usually
including a sub-contract with its contractor member for the
construction of the project (and often also for the design of it)
and its facilities management ("FM") provider member for
provision of management services for the duration of the project,
often 25-35 years. These SPV member subcontractors will in turn
enter into sub-sub-contracts for various aspects of the performance
of the project.
Outside this vertical structure, there will be commercial
bankers providing funding of the project to the SPV. The SPV
absorbs the costs of bidding for and winning the project and
designing and constructing it. The SPV then receives fixed payments
(the "Unitary Charge", which is subject to some
adjustment in some circumstances) for the duration of the project
(say 30 years). These payments cover all the bidding costs, capital
costs, operating costs, financing costs and the profits of the SPV
members.
The typical structure described in Figure 1 is not always
applicable and different structures will give rise to different
relationships between the parties to the project. Figure 1 shows
the typical model as described above and also by way of comparison
Figure 2 shows the model for the M6 toll road, a UK project
discussed further below.
All of these contractual relationships, like any other, may give
rise to disputes. That is not to say that PFI/PPP projects are
particularly prone to disputes nor that other methods of
procurement are immune from disputes. To date, PFI/PPP projects
have not been dispute-ridden, nor is it anticipated that they will
be in the future. However, disputes can and do arise and the
entities involved will require a contractual framework best suited
to the management and avoidance of those disputes.
General introductory matters
Different types of dispute, possible future trends, the normal
contractual provisions for dealing with them and means of avoiding
or managing these disputes are considered below.
It has been convenient to use acronyms, abbreviations and words
with a defined meaning (identifiable by the use of a capital
letter), a list of which appears at the end.
Space has not permitted a detailed discussion of the
shareholders' agreement, regulating the relationship between
members of the SPV. Careful consideration should be given here to
clear risk allocation and, when it comes to dispute resolution, a
tiered system such as is discussed below in relation to the head
contract may also be considered. The issue of conflict of interest
where the same individuals are board members of the SPV and another
company involved in the project, e.g. the contractor or FM
provider, is considered below. General market factors tending
against disputes and factors which may lead to disputes are
considered below.
By way of background to the more detailed discussion which
follows, some introductory explanation of common types of dispute
resolution in PFI/PPP-related contracts, covering their main
features is then set out. There is then a consideration of the
normal dispute resolution provisions in PFI/PPP head contracts, by
reference to the current Treasury standard form, SOPC4, and also to
the Centre for Effective Dispute Resolution ("CEDR")
dispute resolution procedure for PFI and long-term contracts.
After considering these agreements, the writer proceeds to
consider disputerelated issues concerning sub-contracts entered
into by the SPV, including equivalent project relief
("EPR") provisions. The following topics, which are
identified as potential areas for PFI/PPP disputes, are also
discussed below: SPV or contractor/FM provider sub-contracts with
consultants; conflict of interest for directors of the SPV and its
sub-contractors; "interface" agreements (defined below);
bid costs; public procurement issues; and benchmarking and market
testing. The writers conclude with some guidance on areas of
caution and dispute avoidance for the various participants in
PFI/PPP projects.
Features tending against disputes
Disputes between the Authority and the SPV are unusual; the
March 2006 Treasury report recorded that the dispute resolution
procedure has been invoked on few projects, attributing this to
"the fact that relations are strong enough to be able to
resolve issues without normally needing to resort to dispute
resolution." With a typical duration of 30 years, a PFI/PPP
project promotes long-term relationships. Similarly, the SPV
participants have a long-term commonality of interest and are
unlikely to have disputes between themselves.
Because the SPV's funding is provided by bankers who have a
close interest in the proper planning of the project and its
contractual documentation, PFI/PPP projects are typically the
subject of a high degree of design work prior to the construction
phase, high quality budgeting, careful analysis and costing of risk
and detailed and thoroughly considered contractual obligations.
These are factors tending against disputes at the construction
phase, which on traditional procurement has been a fertile area for
contractors' and subcontractors' claims.
Broadly speaking, PFI/PPP projects can be broken down into three
phases: the procurement phase, the construction phase and the
operation and maintenance phase. The construction phase is
traditionally in particular a likely source of disputes. Time and
cost over-runs are some of the most common sources of dispute in
conventionally procured construction projects.
In 2003, a UK National Audit Office ("NAO") Report
found that the percentage of projects where the cost to the public
sector exceeded the price agreed at contract had reduced from 73
per cent (under traditional methods of procurement) down to 22 per
cent under PFI/PPP project procurement. Similarly, the number of
construction projects delivered late to the public sector had
reduced from 70% (pre PFI/PPP) to 24% under PFI/PPP. Whilst no
official statistics have been produced since 2003, unofficial
statistics published on the Building Magazine website indicate that
as at the end of 2008, the number of projects delivered late has
decreased further to 20%.
This does not mean that PFI/PPP projects are delivered at a
lower cost or more quickly than traditionally procured projects,
but it indicates more accurate pricing and programming at the
outset and, therefore, less likelihood of disputes.
Disputes over contractor final accounts, for example, are
uncommon with PFI projects. This is partly as a result of
provisions in PFI/PPP construction contracts which typically
restrict building contractor delay compensation and time relief to
what are described as "compensation events", "relief
events" or "force majeure". These events are
normally much more narrowly defined (and may exclude time and money
and/or relief from liquidated damages) than traditional
"relevant events" and "loss and expense" claims
under the common standard form construction contracts.
One of the reasons for this is the commercial pressure applied
to contractors and the SPV by the banks and lenders through the
security package. PFI/PPP projects also call for construction
requirements to be specified at an early stage in the project which
minimises the prospect of a work scope change during the
construction period - an event that often creates disputes with
conventional procurement. Furthermore, the influence of private
finance (the banks and investors) results in a more rigorous
specification and costing of the construction phase, pre-contract.
Additionally, the construction contractor will frequently be a
shareholder in the SPV and will thus have a direct interest in
ensuring that the construction phase is completed on time and to
budget.
It should be borne in mind that profit margins have been
considerably higher for the construction phase with PFI/PPP
projects than with traditional procurement. Two per cent is a
normal profit margin with traditional procurement, whereas six to
eight per cent has been normal for PFI/PPP projects. The thin
margins in traditional procurement have led to a claimsorientated
industry whereas conversely dispute avoidance is easier where
profit margins are more generous.
The fact that long-term relationships are established by PFI/PPP
projects (typically for 25-35 years) and that the...
To continue reading
Request your trial