The Best Of Intentions: Contract Formation Under Letters Of Intent
In the fast-paced world of construction projects, letters of
intent are a common feature of the contractual landscape. So what
happens if the formal contract being negotiated is never entered
into? We take a brief look at some of the approaches the Courts
have taken in light of a recent decision of the Court of
Appeal.
To view the article in full, please see
below:
Full Article
Where a building project is time-critical (as it often is) and
contractual negotiations are ongoing, it is common for parties to
enter into a letter of intent ("LOI") to
enable the Contractor to commence work before the contract proper
has been finalised. The form and content of LOIs are as varied as
the circumstances in which they may be issued.No doubt it is this
variety that led Robert Goff J in British Steel Corp v
Cleveland Bridge and Engineering Co Ltd (1984) to observe that
there is "no hard and fast answer to the question whether
a letter of intent will give rise to a binding agreement:
everything must depend on the circumstances of the particular
case."
British Steel
British Steel concerned negotiations between British
Steel Corp ("BSC") and Cleveland Bridge
and Engineering ("CBE") for the sale of
steel nodes to be manufactured and delivered by BSC.
CBE issued a LOI, which stated the price and proposed
contractual terms (in the form of the I.C.E. standard form
sub-contract)
The LOI requested that BSC proceed with the work
"pending the preparation and issuing to you of the
official form of sub-contract"
Disagreements subsequently arose between the parties in
relation to the price and other contractual conditions. In
particular, BSC proposed its own standard conditions, which
contained a limitation of liability for late delivery (under the
I.C.E. conditions, liability was unlimited). Although these
disagreements were never resolved, BSC went ahead with production
and delivery of the nodes
CBE refused to pay for the nodes, instead claiming damages for
late delivery
Robert Goff J considered that a LOI could potentially give rise
to 2 different types of contract. However, the judge rejected both
on the basis that the LOI in question applied "pending a
formal sub-contract the terms of which were still in a state of
negotiation". (It was no doubt significant that agreement
had not yet been reached on a number of terms which, on the facts
of the case, were found by the judge to be essential).
Accordingly the Court found that no contract had been concluded
and CBE, as the party who had made the request for performance, was
obliged to pay BSC a reasonable sum for BSC's performance in
accordance with that request. In arriving at this conclusion, the
Court appears to have been particularly swayed by the fact that
both parties were pedalling their standard conditions, which each
took vastly different...
To continue reading
Request your trial