Jurisdictional Challenges: Waiver, Crystallisation And Substantive Issues

The recent case of LJH v Meeresprovides another example of a Court rejecting a parties' attempt to rely on jurisdictional challenges that were not made in the course of the Adjudication. It also acts as a stark reminder not to confuse jurisdictional issues with matters of substance that fall to the Adjudicator to decide and will be enforced by the Court.

The facts

This was a final account dispute in which the Adjudicator decided that Meeres should pay an additional £132,410.83 plus VAT to LJH. Meeres sought to resist enforcement of that Decision on two grounds:

  1. The dispute had not crystallised.

    1.1. This was said to be on the basis that LJH had provided "insufficient information" for its claim to be assessed by Meeres prior to the Adjudication.

  2. There were multiple contracts

    2.1. LJH had wrongly claimed £2,463.75 for works carried out on a different site. Meeres contended that this could not be severed such that the whole Decision should be unenforceable.

    Neither point was raised as a specific reservation in relation to jurisdiction within the course of the Adjudication.

    The decision

    The Court had no difficulty in rejecting these arguments.

    As to the 'crystallisation' point, it held that:

  3. The rejection of a claim on the basis that there is an alleged absence of particularity and / or evidence to support the figures claimed is sufficient to create a 'dispute' in relation to that claim.

  4. The test - as articulated in Amec Civil Engineering Ltd v Secretary of State for Transport [2004] EWHC 2339 (TCC) - is only engaged is the claim is "so nebulous and ill-defined that the respondent cannot sensibly respond to it"

  5. In this case, Meeres had raised specific questions and requests for further information. The Judge held that it had been able to do so because the claim wasnot nebulous or ill defined.

  6. A paying party cannot put off paying up on a claim forever by repeatedly requesting further information; this means that a paying party cannot suggest there is no dispute because the particularisation of the claim is allegedly inadequate.

    As to the 'multiple contracts' point, it held that:

  7. A dispute of fact between the parties as to whether part of the sum was due under a different contract is a...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT