Legal Developments In Construction Law: June 2026
| Published date | 23 June 2026 |
| Subject Matter | Corporate/Commercial Law, Litigation, Mediation & Arbitration, Real Estate and Construction, Contracts and Commercial Law, Arbitration & Dispute Resolution, Construction & Planning |
| Law Firm | Mayer Brown |
| Author | Brad Fearn |
1. Court Considers Contractual Interpretation of Derogation Schedules and Adjudicator's Rights to Assess Extensions of Time
A recent High Court judgment addressed the correct contractual interpretation of bespoke schedules of derogations within amended JCT Design and Build contracts, and whether an adjudicator has the power to fix a completion date earlier than that fixed by the Employer's Agent.
Background and Main Issues
Mace Construct Limited ("Mace") were engaged by Baltic Investment Holdings Limited ("Baltic") under an amended JCT Design and Build Contract 2016 dated 5 December 2023 (the "Contract") for the refurbishment of the Baltic Exchange Building, 38 St Mary Axe, London. The Contract incorporated, amongst other documents, an extensive Schedule of Amendments, a Schedule of Derogations and Tender Clarifications. In December 2024 the Employer's Agent granted Mace extensions of time under the Contract totaling seven weeks and five days. Baltic challenged this grant in adjudication and the adjudicator reduced the extension of time to zero days, concluding the original grant was not binding on him. Mace brought CPR Part 8 proceedings seeking seven declarations on issues of contractual interpretation.
The key issues before the Court were: (i) whether the Schedule of Derogations and Tender Clarifications were incorporated into the Contract; (ii) whether those documents were superseded or overridden by the amended JCT standard terms or had to be given full effect as part of the Contract as a whole; (iii) the extent of Mace's design responsibility for derogation items prior to formal instruction; and (iv) whether an adjudicator has the power to fix a completion date earlier than that fixed by the Employer's Agent under clause 2.25 of the Contract.Incorporation of Schedules of Derogations
On incorporation, Baltic conceded that the Schedule of Derogations and Tender Clarifications formed part of the Contract, and the Court granted declarations accordingly. On the central question of contractual interpretation, the Court held that the Schedule of Derogations was not overridden or modified by amended clause 1.3 of the JCT conditions which addressed priority and primacy of the Contract Documents. The Court reasoned that a "derogation", by its nature, contemplates a partial limitation of an obligation, and that effect had to be given to the entirety of the Contract, including the requirement that formal approval and instruction be received before Mace assumed full design responsibility for the listed items. The Court noted that even if a discrepancy existed, the Schedule of Amendments called up and referenced the Schedule of Derogations which would prevail under clause 1.3(iii). Further clause 1.3(iv) expressly gave primacy to the Schedule of Derogations over the Employer's Requirements. The Court granted declarations sought by Mace in respect of the:
- incorporation of the Schedule of Derogations into the Contract; and
- limitation of Mace's design responsibility for items in that schedule until the required procedures for approval of the design solution of the derogations were approved and instructed by Baltic.
Adjudicator's Power to Fix Earlier Completion
Regarding the declaration as to the adjudicator's powers, Mace had submitted that the JCT extension-of-time provisions in clause 2.25 were conducted on a prospective assessment of the delay and therefore were immune from review by an adjudicator or court as they would be reviewing the situation retrospectively. The Court rejected this submission and held that under paragraph 20 of the Scheme for Construction Contracts (the "Scheme"), the adjudicator has power to "open up, revise and review" the Employer's Agent's decision and must "stand in the shoes" of the Employer's Agent, carrying out the prospective assessment that clause 2.25.1 required, however difficult that may be.
Key Takeaways
Parties negotiating or administering construction contracts should note the following:
- Bespoke schedules of derogations and similar documents will, subject to express drafting of hierarchy-of-documents clauses, likely be given full contractual effect;
- Contractors will not be held to have accepted unqualified design responsibility where the contract provides for a staged approval and instruction process that has not been completed; and
- An adjudicator exercising powers under the Scheme has full authority to review and revise extensions of time, including by fixing an earlier completion date than that granted by the Employer's Agent. Interestingly, even where the assessment of entitlement at the time by the Employer's Agent would have been on a prospective basis, this does not prevent an adjudicator later from having regard to retrospective facts in determining what should be a reasonable extension of time.
Mace Construct Ltd v Baltic Investment Holdings Ltd [2026] EWHC 976 (TCC) (28 April 2026)
2. Successful Party's Refusal to Mediate Was Not Unreasonable, Nor Did It Warrant Departure from Usual Costs Treatment
In a recent costs judgment in the High Court, HHJ Kelly assessed whether a successful defendant's refusal to mediate would prevent costs being allocated in the usual manner and whether the defendant may be entitled to indemnity costs. The judgment followed the dismissal of a professional negligence claim by MJS Projects...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting