What Is The Reasonable Apportionment Of Fault? The Case Of The CNRL Emulsion Pipeline Failure

In Canadian Natural Resources Limited v. Wood Group Mustang (Canada) Inc. (IMV Projects Inc.), 2018 ABCA 305, the Alberta Court of Appeal very recently dealt with an appeal arising from a trial judgment involving a novel, though ultimately faulty, underground oil pipeline. The trial judge found all of the parties to be negligent in some respects, and that the Plaintiff had suffered damages in the sum of $45 million. On appeal, the trial judge's apportionment of responsibility was the principal issue.

The Plaintiff, Canadian Natural Resources Limited ("CNRL"), decided to build a buried 32 km emulsion pipeline between its Primrose East Plant and its Wolf Lake Plant that would carry extra-hot emulsion (a mixture of bitumen, hot water, and steam). Building such a pipeline underground was a singular undertaking that presented new engineering challenges. CNRL retained IMV Projects to provide it with engineering advice on the design and construction of the pipeline. Shaw Pipe supplied the pipe system, which consisted of a steel pipe, an anti-corrosion coating, insulation, and a waterproof outer jacket. Flint Field Services was retained to install the pipe. The emulsion pipeline had a life expectancy of 30 years. It failed after about three months of operations.

On the eve of trial, CNRL entered into Pierringer agreements with Shaw Pipe and Flint Field Services. Hence, the trial only proceeded against IMV Projects. While the legal liability of Shaw Pipe and Flint Field Services was no longer in issue, their responsibility for the damage to the emulsion pipeline still had to be determined in order to apportion responsibility to the various tortfeasors. The trial judge found that each of CNRL, IMV Projects, Shaw Pipe, and Flint Field Services were in some respects negligent, resulting in the eventual failure of the pipeline.

The pipeline failed for two basic reasons: flawed design and operational error. Firstly, it quickly became apparent that the pipeline system (supplied by Shaw Pipe with the approval of IMV Projects, and selected by CNRL) was very vulnerable to water penetrating the waterproof outer jacket. The insulation was permeable, and any water that leaked through the waterproof outer jacket would eventually find its way through the insulation to the steel pipe. Since the emulsion in the pipe was well over 100°C, when that water touched the steel pipe it would vaporize explosively, expand in volume, and damage the surrounding insulation. That...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex