If It Ain't Broke Don't Fix It - Contract Interpretation After Chartbrook v Persimmon
The recent House of Lords decision in Chartbrook v Persimmon,
with Lord Hoffman delivering the leading judgment, confirmed that
the rules for contractual interpretation remain:
what a reasonable person, having all the background knowledge
which would have been available to the parties, would have
understood them to, by using the language in the contract,
mean.
pre-contract negotiations are inadmissible for the purpose of
interpreting a contract.
It is a little unusual that a case which decides nothing new
creates so much interest in the legal community. It might be
thought that the reason Chartbrook v Persimmon has done so may be
due to the fact it is the last decision of Lord Hoffman sitting on
the House of Lords Judicial Committee. However, that would be to
vastly underestimate the usefulness of the case and the
comprehensive review of the rules undertaken by Lord Hoffman.
Dispute
Knowing the nature of the actual dispute that was decided is not
all that important but, for what it is worth, it related to the
price to be paid by a developer to a land owner in relation to
property built on the land when the property built was sold. The
dispute required interpretation of a clause that provided for
additional sums to be paid by the developer to the land owner if
the price achieved on sale exceeded an anticipated amount. The
question was whether a particular deduction from the sale price was
applied before or after calculating the percentage of the price to
be paid to the landowner by the developer .This question was worth
about 3.5 million pounds.
The House of Lords decided that it should not interpret the
clause according to the normal rules of syntax as it made no
commercial sense to have the clause read in that way. Also, such an
interpretation rendered other parts of the contract arbitrary and
irrational. Accordingly, the House of Lords ruled in favour of the
developer paying the land owner on the basis of the contract
interpretation that led to less money being due to the land
owner.
Reasoning
Lord Hoffman started from the point that the well established
rule of contract interpretation is what a reasonable person, having
all the background knowledge which would have been available to the
parties, would have understood them to mean when using the language
in the contract. The House of Lords had said previously that it did
not easily accept that people have made linguistic mistakes,
particularly in formal contracts, but that in some cases the court
was driven to the conclusion, from looking at the background and
context, that something had gone wrong with the language of the
contract. However, it required a strong case to persuade the court
that such a thing had happened.
Lord Hoffman considered that where the court was driven to the
conclusion that something had gone wrong with the language, whether
with the meaning or the syntactical arrangement, it doesn't
matter that the meaning the court must give the words does not
reflect the conventional meaning of the words. The job of the
court, in such a case, is to...
To continue reading
Request your trial