BLG Commercial Dispute Resolution Briefing, April 2009
Arbitration
Court's Role Is To Support, Not Supervise, The
Arbitration
John Forster Emmott v Michael Wilson & Partners Limited
(2009)
The High Court has clarified that its role is, wherever
possible, to support arbitrators' decisions, rather than to go
behind them and consider whether the relevant order should have
been made. In what appears to be the first reported case of this
kind, the applicant ("E") applied to the High Court under
section 42 of the Arbitration Act 1996 (the "Act") for an
order enforcing the arbitral tribunal's order. E's dispute
with the respondent ("M") arose out of an agreement
between them to establish an independent legal and business
consultancy in Kazakhstan and involved allegations that E was
entitled to a certain percentage of profit and shares in M. M
counterclaimed, alleging that it was entitled to a 27 per cent
shareholding in a separate company. The tribunal ordered that
M's 27 per cent shareholding be held to the order of the
chairman of the arbitral tribunal. M failed to comply and E applied
to the court for the order to be enforced as well as for a freezing
order against M.
The Court enforced the tribunal's order, emphasising that
the circumstances where it would refuse to do so were limited.
These were where the interests of justice required it, as a result
of a material change in circumstances for example, or where the
tribunal had acted unfairly or outside its powers. It would be
inconsistent with the general principle that the court should not
intervene in arbitrations to, in every case, review the decision
made by the tribunal and consider whether it ought to have been
made. The court could only review the arbitral process properly
under sections 67-69 of the Act, which permit challenges to the
tribunal's jurisdiction and challenges based on procedural
irregularity or error of law.
Two points of detail are worth noting. Firstly, the Court
clarified that shares were within the definition of
"property" in section (s.38(4)) of the Act under which
the tribunal had made its order. Secondly, and illustrating its
desire to support rather than interfere with arbitration, the Court
willingly granted the freezing order sought, but made it clear that
any application regarding it (for its variation or discharge, for
example) must be made directly to the arbitral tribunal rather than
the Court.
www.bailii.org/ew/cases/EWHC/Ch/2009/1.html
Allianz and Another v West Tankers (2009)
The European Court of Justice (the "ECJ") has
clarified that it is not appropriate, under European Council
Regulation No 44/2001 (the "Regulation"), for one EU
member state court to order the court of another member state to
halt proceedings issued there in alleged breach of an arbitration
agreement. This firmly puts an end to the previous practice of the
High Court issuing anti-suit injunctions in support of pending
English arbitration proceedings. The ECJ stressed that the
Regulation gives member state courts power to rule on their own
jurisdiction and the validity and applicability of the arbitration
agreement. Anti-suit injunctions obstructed the exercise of this
power.
See the BLG briefing note for more detail on this case,
available at
www.blg.co.uk/pdf/West%20tankers.pdf
Contract
Tele2 International Card Company SA and others v Post
Office Limited (2009)
A party's delay in reacting to a breach of contract may risk
him waiving his right to terminate the contract. In this case, some
of the claimants supplied phone card services to the Post Office
and were obliged under the contract to provide parent company
guarantee letters to the Post Office each year. During 2003, the
claimants in question failed to provide the letters, committing a
technical breach of contract, but the Post Office failed to react
and the parties continued to perform under the contract. Nearly a
year later, the Post Office purported to terminate the agreement by
written notice for failure to provide the letters. The High Court
agreed with the claimants' argument that the Post Office had
affirmed the contract by continuing to perform under it without any
protest concerning the breach or seeking to reserve its rights. As
a consequence, the court held that the Post Office had in fact
committed a repudiatory breach of contract by terminating the
contract and ceasing to perform its obligations. The claimants
were, however, not entitled to damages, as on the facts of this
case they had not suffered any loss.
http://www.bailii.org/ew/cases/EWCA/Civ/2009/9.html
Graeme Grant v Russell Bragg, Russell Bragg and Premier
Resorts Ltd v Graeme Grant (2009)
If parties intend to enter into a contract, a court will usually
find that a contract has not been concluded until both parties have
signed the necessary documents, but this case demonstrates that
this is not always the case, and the court may take a more flexible
approach.
In this dispute between two shareholders, "G" and
"B", both 50 per cent shareholders and directors in a
company, the issue was whether there was a concluded contract that
B would buy G's shares. A draft sale and purchase agreement
("SPA") had been drawn up but was not signed. However,
the High Court held that there was, nevertheless, a concluded
contract since the parties had exchanged e-mails agreeing to the
terms of the SPA and B had taken control of the company,
effectively taking the benefit of G's shares. The Court found
that it would be to deny commercial reality and the objective
intention of the parties to hold that they were not contractually
bound in the absence of an executed document.
In light of this ruling, parties are well advised (where they do
not wish to be contractually bound) to make it clear that their
negotiations are "subject to contract". Furthermore,
where parties are to perform the contract before the documentation
has been entered into, the parties should ensure that the basis on
which they do so is made clear.
www.bailii.org/ew/cases/EWHC/Ch/2009/74.html
RTS Flexible Systems Ltd v Molkerei Alois Müller
GmbH & Co KG (2009)
This Court of Appeal decision contrasts with the flexible
approach adopted by the High Court in Grant v
Bragg (above). In this case, the Court of Appeal
ruled that a contract had not come into existence because the
parties had failed to comply with a formality. The defendant,
Molkerei Alois Müller (a producer of dairy products)
contracted with the claimant for the design and supply of equipment
for one of its factories. The claimant started work on the basis of
a letter of intent issued by the defendant. The claimant continued
to work on the project despite the letter of intent having expired
and even though the parties had not reached agreement on the
wording of a draft contract. The Court of Appeal had to consider
whether there was in fact a contract between the parties or whether
(as alleged by the claimant) there was no contract and the claimant
ought simply to be paid for the work it had carried out.
The Court held that there was no contract because the draft
unsigned contract contained a counterparts clause stating that the
final contract would not be effective until each party had executed
a counterpart and exchanged it with the other, and that the parties
had clearly agreed to negotiate on this basis. In effect, the Court
held, there was a continuing stipulation that a contract would not
come into force until the documents were signed and exchanged.
Despite this decision, we would suggest it is still preferable
for parties to make it explicit whether or not negotiations are
"subject to contract".
www.bailii.org/ew/cases/EWCA/Civ/2009/26.html
Stocznia Gdynia SA v Gearbulk Holdings Ltd
(2009)
This Court of Appeal decision clarifies that if a party wishes
to prevent another party from asserting its common law rights upon
breach of contract, it must express this clearly in the wording of
the contract.
The appellant, Gearbulk, entered into contracts for the
construction of ships by the respondent. An article of the contract
allowed for the purchase price to be reduced for delays in delivery
and permitted Gearbulk to terminate for a major...
To continue reading
Request your trial