Can The Court Order Payment Of The Adjudicator's Valuation, Where The Adjudicator Lacked Jurisdiction?

Published date31 August 2023
Subject MatterCorporate/Commercial Law, Litigation, Mediation & Arbitration, Real Estate and Construction, Contracts and Commercial Law, Trials & Appeals & Compensation, Construction & Planning
Law FirmBarton Legal
AuthorMr Bill Barton

The assumed answer is no, due to a party's ability to challenge an adjudication where the Adjudicator has no jurisdiction. However, the correct answer is yes, as set out in WRW Construction Limited v Datblygau Davies Developments Limited [2020] EWHC 1965 (TCC).

The employer, Datblygau Davies Developments Limited ("Employer") appointed the contractor, WRW Construction Limited ("Contractor") under a standard JCT Design and Build 2011 contract ("the Contract") to design and build nine residences in Twickenham, London.

Due to various issues on the project, the Employer terminated the Contract in mid-2018. There were three adjudications in total, and in the second the Adjudicator decided the Employer had validly terminated the Contract.

Subsequent to this, the Employer issued a third final account adjudication (post termination) on 7 February 2020. The relief sought by the Employer in the Notice of Adjudication was for the Contractor to pay a sum of over '3million to the Employer as damages for breach of Contract and/or per clause 8.7 of the Contract.

Clause 8.7 of the Contract stated as follows:

"8.7.4 Following the completion of the Works and the making good of defects in them (or instructions otherwise as referred to in Clause 2.35), an account of the following shall within 3 months thereafter be set out in a statement prepared by the Employer:

8.7.4.1. The amount of expenses properly incurred by the Employer, including those incurred pursuant to Clause 8.7.1 and, where applicable, Clause 8.5.3.3, and of any direct loss and/or damage caused to the Employer and for which the Contractor is liable whether arising as a result of determination or otherwise;

8.7.4.2 The amount of payments made to the Contractor; and

8.7.4.3 The total amount which would have been payable for the Works in accordance with this Contract;

8.7.5 If the sum of the amount stated under Clauses 8.7.4.1 and 8.7.4.2 exceeds the amount stated under Clause 8.7.4.3, the difference shall be a debt payable by the Contractor to the Employer or, if that sum is less, by the Employer to the Contractor".

The Notice of Adjudication required the Adjudicator to determine the sums payable by the Contractor (which were to be paid within 7 days of the Adjudicator's decision), and to order the...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT