Construction Professionals: Disclosure To Insurers
A recent case gives guidance on what constitutes
circumstances that construction professionals should disclose
to insurers at renewal.
A Mechanical and Electrical Sub Contractor, LVE, did not
disclose problems it was having with its contractor to its
legal expenses insurer, Templeton, at renewal. Shortly after
renewal, it did notify the problems as a potential claim.
Templeton denied cover as it claimed that (a) LVE failed to
disclose material circumstances known at renewal and (b) LVE
failed to comply with the claims notification procedure - a
breach of condition precedent under the policy entitling
Templeton to decline an indemnity.
HHJ Hegarty QC, in finding against Templeton, and deciding
that LVE was entitled to cover, held:
By the date of renewal of LVE's policy, the
relationship between LVE and the contractor had not
deteriorated to the stage where it was properly to be
regarded as a material circumstance that was likely to give
rise to a claim, which would have required notification to
Templeton
A formal claim would have appeared 'likely' if
discussions and correspondence had indicated that the
differences between the parties would lead either to
adjudication, arbitration or litigation
A threat from the main contractor to 'replace'
LVE as sub-contractor did not, on these facts, constitute a
material circumstance that would be likely to lead to a
claim
Complex construction contracts inevitably give rise to
disputes as to the progress of works, sums due to the
contractor and quality of the work. This project was no
different, and discussions to resolve such disputes between
the contractor and LVE on the project in question appeared to
be amicable and constructive
An insurer is presumed to be aware of the general risk
that construction contracts may give rise to disputes and
differences between contracting parties. Therefore, something
more serious is required before a particular problem is to be
regarded as a material circumstance that must be disclosed at
the time of initial proposal or renewal. Otherwise insurers
must expect to be bombarded with notifications on every
single construction issue
A letter from the contractor to LVE after renewal, which
said, "unless we are able to reach mutual agreement,
this will have to be referred to arbitration in accordance
with the contract", did constitute a material
circumstance that should be disclosed to insurers.
The court therefore took a pragmatic and sensible view of
what should and...
To continue reading
Request your trial