Court Of Appeal Confirms Jurisdiction To Award Claimant Interim Payment On Account Of Costs Where Part 36 Offer Accepted Within Relevant Period

The Court of Appeal has unanimously held that the court has jurisdiction to order an interim payment on account of costs pursuant to CPR 44.2 where a Part 36 offer has been accepted within the relevant offer period, overturning the High Court's decision that there was no such jurisdiction: Global Assets Advisory Services Ltd v Grandlane Developments Ltd [2019] EWCA Civ 1764.

The Court of Appeal's decision is significant as it clarifies that claimants in such circumstances, where a costs order is deemed made in the claimant's favour, can obtain an interim payment on account of costs as if there were an actual costs order in their favour. It means that, in appropriate cases, claimants will be able to recover part of their costs without having to wait for the conclusion of the (often protracted) process of detailed assessment or negotiations to agree the quantum of costs.

Sarah Boyle, an associate in our disputes team, considers the decision below.

Background

The claimants made a Part 36 offer to settle their claim. The defendants accepted within the "relevant period" for the purposes of CPR 36.13, so the claimants were deemed to be entitled to the costs of the proceedings up to the date of acceptance under CPR 44.9.

The claimants produced a draft consent order which included an order for an interim payment on account of costs. The defendants objected to the inclusion of the order for an interim payment, and the claimants submitted an application seeking such an order.

The High Court (Teare J) noted that, in Finnegan v Spiers (t/a Frank Spiers Licensed Conveyancers) [2018] EWHC 3064, Birss J had found that there was no jurisdiction to make an interim order for payment on account of costs where a Part 36 offer had been accepted within the relevant period and a deemed order for costs had arisen under CPR 44.9. Teare J said it was his duty to follow the earlier decision, as he could not say he was convinced that it was wrong. However, he gave permission to appeal as he considered that the arguments to the contrary were substantial.

In summary, in Finnegan v Spiers, Birss J held that:

Part 36 is a self-contained code which deals with all the costs consequences where a Part 36 offer is accepted, and would accordingly be the place to find the power to award interim payments if such power existed. The power to order interim payments on account of costs under CPR 44.2 applies where a court has ordered a party to pay costs. It does not...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT