COVID-19 Effects On The Construction Industry

Published date23 December 2021
Subject MatterReal Estate and Construction, Coronavirus (COVID-19), Construction & Planning, Litigation, Contracts and Force Majeure
Law FirmMMA Law
AuthorMMA Law

Construction projects are dependent on the flow of materials, equipment, and labor along supply chains. A disruption at any level has the potential effect of delaying delivery and increasing costs. The COVID-19 outbreak and the subsequent measures taken to contain it have had a profound impact on every industry including construction. As lockdowns all over the world are entering a phase of easing and economic activity is resumed, contractors are facing the challenge of financing increased costs and the uncertainty of whether those are covered by contract clauses and can be recovered.

All over the world, construction projects came to a halt, have not started, or accumulated important slowdowns and delays. With little to no guidance relating to pandemics, parties are contrasting contract clauses against regional and national common laws. Most standard contract forms like versions of FIDIC have an explicit force majeure clause (1999 edition), or at least an equivalent "exceptional event" clause (2017 edition). However, situations occur where contracts either do not mention force majeure at all or mention it without discussing epidemics and pandemics. Even so, most standardized contracts do allow for excusable delays that could be applied successfully to the COVID-19 case.

There is almost a consensus that given the scale and speed of the COVID-19 crisis, where it is possible, it meets all criteria to qualify as a force majeure event. However, in some jurisdictions, the current definition is likely to be too narrow to incorporate all contract issues. For example, in the UAE for an event to qualify as force majeure it must be unforeseeable, its effects must be incapable of prevention, and it must render performance absolutely impossible. The last condition contradicts the reality of many construction projects where performance has now become rather burdensome and costly, but not impossible.

Inconsistency of entitlement can also arise where different contracts in a chain have different overarching governing laws. This can lead to uneven relief rights. The situation is to be expected on important international projects involving companies from different countries and multiple levels of subcontracting. The force majeure clause is often put against the "change in law" provision many contracts have. Because they would otherwise be granted only a time extension, contractors are asking whether the change in laws many countries...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT