PFI/PPP Disputes - Part 3
Procedural requirements
Claimants are required to inform the contracting authority of
the nature of the alleged breach and that they intend to commence
proceedings. This is a strict requirement and failure to adhere to
it will render any action inadmissible.
The Regulations require that proceedings be brought promptly
and, in any event, within three months from the date when the
grounds for commencing the action first arose save where the court
believes that there is good reason for allowing an extension to
this period. The UK courts (See Jobsin Co UK plc v Department
of Health [2001] EU.L.R 685) have determined that even in
circumstances where the three-month time limit is met such actions
may not be prompt enough. Accordingly, a party meeting the
three-month time limit is no guarantee of the courts allowing the
proceedings to commence. In Holleran v Severn Trent Water
[2004] EWHC), it was held, in respect of an application for an
injunction, that "prompt" meant that a complaint should
be brought within a "few days". However, where the
claimant brings an action seeking damages and not an injunction to
restrain a contract award, it is likely that the courts will not
take such a strict approach. The limitation period set out in the
Regulations has no regard to whether or not the potential claimant
had relevant knowledge that he was in a position to commence
proceedings.
Overlap with Judicial Review?
The remedies set out within the Regulations are expressly
provided to be "without prejudice to any other powers of the
courts". Seemingly, therefore, tenderers are able to seek to
challenge public sector procurement decisions by way of judicial
review. In order to do so the claimant would need to establish that
the decision made had a sufficient public law element so as to give
rise to judicial review proceedings. The disgruntled party must
have a "sufficient interest" in the matter. The central
question is, therefore, what amounts to a "sufficient
interest"?
The UK courts gave consideration to the availability of judicial
review in Hibbert & Sanders [1992] COD. The court
held, in that case, that judicial review was not available
principally because the decision in question was not a matter of
public law but was one that sat entirely within the realm of
private law. The court considered that there must be a specific
element of public law to ensure that the decision could be
challenged in this way following the decision in R v East
Berkshire Health Authority ex parte Walsh [1985] 1 QB 152. The
courts concluded that simply because the Regulations impose
obligations on a public body, that does not in itself mean that
judicial review would be available. Rather, Judicial Review will
only be available where the courts can find some special
"public law interest" to justify a judicial review. A
different approach was taken in the Northern Irish case of
Leonard Personnel Limited [2008] NIQB 63 where the
Northern Irish High Court accepted that the fact that the
regulations impose a duty on public authorities to act objectively,
fairly and transparently may give rise to the requisite public law
interest. It will be interesting to see if the courts adopt the
position taken in Leonard Personnel. Professor Sue
Arrowsmith has been critical of the decision in Hibbert &
Sanders. Her view is that the UK courts have been inconsistent
in their approach. She suggests that the better approach would be
that, in principle, contracting powers are subject to public law
principles of judicial review in exactly the same way as all other
powers of government.
The CPR pre-action protocol for judicial review states that
where an alternative procedure is available which has not been
used, the court has a discretion to refuse leave for judicial
review. The judge's decision as to whether or not leave should
be given would depend upon the circumstances of the case in hand,
which would include consideration of the nature of the alternative
remedy available.
Non-financial remedies
Specific provision is made in the Regulations for an injunction
to suspend the award procedure or suspend the implementation of any
decision and also for an order which would set aside a decision
made by a contracting authority. This is discussed above in the
context of the Alcatel judgment. One important exception
to the prohibition of setting aside a contract which has already
been awarded may exist in circumstances where there might have been
some bad faith or collusion between the contracting authority and
the contractor, so as to breach the procurement laws.
The current legal position is, generally, that once a contract
has been concluded, a claimant is limited to damages as its remedy.
Once Directive 2007/66 has been introduced into English law,
however, this position will change. The Directive requires member
states to allow claimants to seek a declaration that a concluded
contract is ineffective, where the contracting authority has either
awarded a contract without holding a competition at all, or where
it has concluded the contract without observing the ten-day
"Alcatel" standstill obligation (see above). The
OGC is currently consulting stakeholders over how
"ineffectiveness" should be implemented into national
law. There are two possibilities as to the meaning of
"ineffectiveness": the existing contract could be
ineffective from the start, as a matter of retrospective effect; or
it could be ineffective as to the future from the time of the
decision of the court. The OGC does not favour the former approach,
because of the legal and practical difficulties surrounding a party
who, without fault, has been operating under a contract wrongly
awarded by the contracting authority. The latter approach, which is
favoured by the OGC, would be easier to administer.
There is some evidence that, even in advance of the
implementation of the Directive, courts will be willing to set
aside concluded contracts if certain key aspects of the procurement
rules are not observed. In the unreported, Scottish case, D.R.
Plumbing & Heating Services v. Aberdeen City Council
(2009), the Court of Session cancelled a concluded agreement as the
contracting authority had not observed the Alcatel obligation in
the foregoing award procedure.
Damages
The Regulations do not set out in any detail the basis upon
which damages for breach of the procurement rules could be
quantified. Case law suggests that there are two main heads of
potential loss. These are loss of tender costs and loss of profit.
As stated above, the Court's approach in Aquatron was
to take the approach that as a successful tenderer re-coups its bid
costs as part of profits made in performing the contract, the
correct approach was to allow a claim for loss of the
claimant's profits on the contract.
English courts will take into account the probability
that, but for the breach, the entity claiming damages would have
succeeded in being awarded the contract. The courts will look at
what profit the claimant might have made from the contract had it
been successful and then will assess the claimant's chances of
being awarded the contract in question. By way of example, the
court might decide that there was a 60 per cent chance that the
claimant would have been awarded the contract and therefore award
60 per cent of the calculated profit as damages. The aim of the
court is to reduce the value of the benefit which has not been
received or the full cost of the risk incurred in a manner
proportionate to the degree of likelihood that the benefit or risk
would have been gained or indeed avoided. (Additional judicial
guidance on the evaluation of a loss of chance was given in the
Harmon case referred to above.)
Article 226 proceedings
In addition to an action in the national courts either by way of
the regulations or by means of a judicial review, a disgruntled
party has the option to lobby the European Commission so as to
encourage them to act as a consequence of the breach of the
procurement rules. If the Commission is of the view that a member
state has failed to fulfil its obligations under the EU Treaty,
there is a possibility that it would commence proceedings under
Article 226. In practice, because of the Commission's extremely
limited resources, relatively few Article 226 proceedings are
commenced.
Benchmarking and market testing
Benchmarking
Benchmarking and market testing are terms applicable in the
context of the work of the FM provider in relation to soft
services. "Benchmarking" means the process by which the
SPV derives information about costs in the market place as a basis
for comparison with its own costs or those of its FM provider
sub-contractor for the provision of soft services. This may lead to
either an adjustment in the payments to the SPV and therefore the
FM provider, or it may lead to the provision of soft services by
others. Soft services need not be included at all in PFI/PPP
projects; the government department has the option of not
transferring soft services staff for PFI/PPP projects, if it is not
considered necessary or desirable in the overall interests of the
project, or value for money. Where soft services are included,
benchmarking and/or market testing may be, but need not be, part of
the contractual terms of the project agreement.
The PFI/PPP market in the UK has only recently begun to attain a
level of maturity such that the earlier projects have reached the
stage at which benchmarking and market testing are undertaken.
...
To continue reading
Request your trial