Adjudication: The Case Of Dorchester vs Vivid Raised The Familiar Question Of When An Adjudication Breaches Natural Justice. Here Is What The Judge Had To Say....Fair Enough?
A feature of adjudication now sadly familiar to practitioners is
the way in which some referring parties apparently try to hamper
the respondent's ability to respond to the claim. With short
time limits in play some will choose the most inconvenient time to
launch an adjudication and serve vast quantities of documents -
behaviour which sometimes resembles ambush by steamroller.
In Dorchester Hotel Limited v Vivid Interiors Limited
(19.01.09) Mr Justice Coulson was faced with an adjudication in
which he clearly felt this was going on. Vivid had been engaged by
Dorchester to carry out refurbishment in its hotel. The final
account was in dispute. On 19th December, the Friday
before Christmas, Vivid commenced adjudication proceedings. The
Referral Notice, itself ninety two pages long, was accompanied by
thirty seven lever arch files which included six substantial
witness statements and two experts' reports of thirty and
twenty pages each. Whilst it appears that much of this extensive
material was not entirely new at least five files were and many of
the individual figures within the final account had been recast or
revised.
The adjudicator was only prepared to accept the reference if
Vivid agreed to disregard the holiday period from 24th
December to 4th January for the purpose of the twenty
eight days within which the adjudication had to be concluded. Vivid
agreed and in addition agreed a further extension to 28 February
with a timetable which required Dorchester to respond to the claim
by 28th January. However beyond that Vivid was not
prepared to go.
Dorchester said this timetable was too tight and claimed there
was a very real risk of there being a breach of natural justice.
Using Part 8 procedure under the Civil Procedure Rules it sought
declarations to that effect. Mr Justice Coulson said this raised
the novel question of the extent to which the court should
intervene in an ongoing adjudication in connection with potential
breaches of the rules of natural justice.
The judge clearly sympathised with Dorchester. He said that
Vivid had commenced the adjudication in the way it had in order to
obtain the greatest possible advantage from the summary
adjudication procedure. He added that it was a matter of regret
that the adjudication process, which was itself introduced as a
method of dispute resolution which would avoid unnecessary legal
disputes and procedural shenanigans, was now regularly exploited in
the same way. He also expressed...
To continue reading
Request your trial