Energy Regulation April 2008 Updates
FERC Affirms And Clarifies New Market-Based Rate
Policy
FERC, acting on rehearing of its market-based rate
rulemaking proceeding Order No. 697, largely affirmed its
earlierrulings, including its decision to utilize a
regional approach for the triennial market power analysis
(separating the nation into six geographic regions); the
adoption of horizontal and vertical power analyses; the use of
a balancing authority area or the regional transmission
organization/independent system operator market as the default
relevant geographic market; and the codification of
restrictions on affiliate abuse in the regulations. FERC stated
that this will strengthen wholesale power markets and protect
customers from exploitation in those market.
The rehearing order also clarifies the horizontal market
power analysis. While FERC affirmed its continued use of
historical data and a "snapshot in time" approach, it
stated that it also will consider case-specific sensitivity
studies that present compelling evidence that certain changes
in a market should be considered as part of the market power
analysis. Finally, FERC will allow mitigated sellers to
demonstrate on a case-by-case basis that they do not have
market power with respect to long-term contracts.
Transmission Owners Can Choose To Pay 100 Percent Of
Network Upgrade Costs In Midwest Independent System Operator
(ISO)
FERC has denied rehearing of an order that allowed three
transmission owners: International Transmission Company,
Michigan Electric Transmission Company, and American
Transmission Company, to pay 100 percent of network upgrade
costs needed to interconnect a new generation facility to their
transmission facilities. These costs can be received through
transmission rates under the Midwest ISO tariff.
The Midwest ISO's tariff generally requires the
interconnection customer itself to pay 100 percent of the
upgrade costs, with possible recovery of 50 percent of those
costs. In this docket, FERC accepted tariff changes that also
allow transmission owners to choose to pay 100 percent of the
network upgrade costs, rather than the generator. Of the 100
percent paid by the transmission owners, 50 percent is eligible
for recovery through tariffed regional cost-sharing measures
and 50 percent can be recovered automatically through zonal
transmission rates.
Several Michigan utilities, consumer groups, and the
Michigan Public Service Commission requested rehearing of
FERC's order accepting these tariff changes. They argued
that transmission companies have incentives to over-invest in
transmission infrastructure, which subjects existing
transmission customers to unnecessary rate increases. They also
argued that customers will be forced to pay for network
upgrades that provide no benefit if the interconnection
customer decides to serve load outside the Midwest ISO region
after its one-year minimum term of service is met. FERC
rejected these arguments as well as the request that a cap be
imposed on interconnection costs eligible for reimbursement,
finding that network upgrades benefit all customers by
providing a more competitive generation market.
Incentive Rate Treatment For Transmission Projects Varies
In Recent Cases
In the past two months, FERC has issued a series of orders
implementing Order No. 679's policy of allowing public
utilities to obtain incentive rate treatment for transmission
infrastructure investments that meet certain criteria. The
applicant must be able to demonstrate a nexus between the rate
incentive requested and the particular risks of the
project.
In a recent case applying the incentive rate policy
involving a 130-mile, 500 kV transmission line (Susquehanna
Line) of PPL Electric Utilities Corporation and Public Service
Electric & Gas Company, FERC approved with two
partial dissents a 1.25 percent return on equity adder,
a 0.5 percent adder to each utility's base return on equity
for continued membership in PJM, full recovery of prudently
incurred Construction Work in Progress (CWIP) expenses in rate
base, abandonment incentives if the project does not go forward
to completion, and authority to transfer certain incentives to
affiliates in the future.
FERC action in other incentive rate cases:
On PG&E's proposed 1,000-mile transmission
project from...
To continue reading
Request your trial