Force Majeure Clauses In Construction Contracts
The primary purposes of construction contracts are to
clarify responsibilities (including performance and payment
obligations) and to allocate risk. It is in regard to the
latter purpose that the concept of force majeure plays
an important role. Such clauses serve to deal with the risk of
events which fall short of frustration. Such clauses can be
successfully employed to recognize industry or project specific
risks. By way of example, a number of years ago the writer
dealt with a pipeline claim that arose from the delayed
completion of a series of compressor stations and a connecting
pipeline through the southern interior of British Columbia.
Perhaps the biggest risk on that, and perhaps on any pipeline
project, was the inability to reasonably manoeuvre and work on
the pipeline right away. As matters transpired, the work was
done during an extremely rainy summer. Although very unusual,
the amount of rain did not approach one in one hundred year or
other bunch numbers that would have clearly have resulted in a
force majeure event having been triggered.
Nevertheless, the work became very slow and very expensive to
complete. Only after extensive negotiation and litigation
preparation were the potential claims arising from the cost and
time of performance resolved. Had the force majeure
clause in the contract been drafted with the specific project
and type of work risk in mind, the dispute could have readily
been avoided.
At the time of writing, there are serious shortages of both
labour and certain materials in Canada, though the shortages
are more acute in some areas of the country than others.
Oilsands project construction in Alberta, pre-Olympic
construction in British Columbia and general economic expansion
in Saskatchewan have all lead to shortages in Western Canada.
On other hand, the competition for steel, specialty metals and
specialty pressure vessels throughout North America, arguably
caused in part by competition from the rapidly expanding
economies of both China and India, has focused the need for the
careful examination and drafting of both force majeure
and other risk allocation clauses within construction
contracts.
The issue is highlighted in Alberta where there is a fear
that labour shortage could be advanced as a force
majeure event. These circumstances have sparked some
owners of large projects to specifically exclude labour
shortage as an event of force majeure. This,
apparently, despite such shortage neither falling within the
idea of the "...unexpected, something beyond reasonable
foresight or skill"1 and despite the fact that
many cases in all three of Canada, England and the United
States have held the changes in market conditions are not
sufficient to fall within a standard force majeure
clause2.
In other areas, rather than face arguments that a force
majeure event has occurred due to the material shortage,
risk allocation clauses have been formulated to specifically
address shortages of such materials as steel. For example, a
provision written on behalf of the American Institute of Steel
Construction provides as follows:
The subcontract price is based upon the agreed prices and
surcharges for the steel types and shapes necessary for the
project and posted and made publicly available by [steel
mill] on [date]. Notwithstanding anything herein to the
contrary, any increases or decreases in the price of the
steel ordered by subcontractor for the project, or any
additional surcharges imposed on the steel ordered by
subcontractor for the project, after [date] shall result in a
corresponding dollar-for-dollar increase (or decrease) in the
subcontract price.3
It is the intention of this article to highlight elements
that require careful and specific consideration of the drafting
of force majeure clauses.
-
Purpose of Force Majeure
Clauses
Force majeure clauses exist to exclude liability
where unforeseen events beyond a party's control prevent
the performance of its contractual obligations. The Supreme
Court of Canada in Atlantic Paper Stock Ltd.
v. St. Anne-Nackwawic Pulp & Paper
Co.4, the leading Canadian force
majeure decision, describe the purpose of force
majeure clauses as follows:
[A force majeure clause] generally operates to
discharge a contracting party when a supervening, sometimes
supernatural, event, beyond the control of either party,
makes performance impossible. The common thread is that of
the unexpected, something beyond reasonable human foresight
and skill.5
The term "force majeure" has been
variously described elsewhere as meaning an "irresistible
force", an "unforeseen event", an "over
powering force", or "a fact or accident which human
prudence can neither foresee nor prevent."6 Put
another way, force majeure events are generally
considered to be events "beyond the control and without
the fault or negligence" of the party
excused.7
While the "irresistible" forces contemplated by
force majeure clauses typically include such things as
wars, natural disasters (and other "acts of God")
they can also include more conventional commercial events such
as the failure of supplies, forms of labour unrest and
equipment failure.
The term "force majeure" is derived from
civilian law and encompasses a concept now entrenched in
several legal traditions, including the lex
mercatoria.8 Its presence in Anglo-American
contract law can be directly traced to French Code
Civil.9 Force majeure is based on the
concept that it is fair to allow a party to escape contractual
obligations without fault when satisfaction of those
obligations is made impossible. Rather than being a universally
applicable concept as in French jurisprudence, however,
"force majeure" in the Anglo-American
tradition is a purely contractual right to the suspension or
release of one's contractual obligations upon the happening
of certain defined events.
Though related to the common law doctrine of contractual
frustration, force majeure can be applied much more
broadly and flexibly. The late 19th century
Queen's Bench decision in Jacobs v. Crédit
Lyonnaise10 illustrates this point. There, the
defendant shippers claimed force majeure after it
failed to deliver esparto shipments owing to a war that had
broken out in Algeria. Under French law, then in force in
Algeria, the defendant would not have been subject to claims of
damages "when, by means of a superior force (force
majeure) or an accident, the obligor has been prevented
from giving or doing that which he was bound to give or
do."11 The English Court found that while
French law may have given relief, English law applied and there
was no equivalent common law principle (including frustration)
that could ground relief. While the intervening war had
disrupted performance, it did not destroy the "entire
subject matter" of the contract or the underlying rational
for the bargain as was required for relief under the doctrine
of frustration. The contract did not provide force
majeure, and the defendant shippers were held liable.
About the same time and likely in recognition of the
harshness of the result in Jacobs, explicit force
majeure provisions began to appear regularly in English
contracts.12 The emergence of contractual force
majeure provisions arose, at least in part, as a means to
provide relief from contractual obligations where performance
is rendered impossible or unfeasible, but where the strict
technical requirements for a defence of frustration are not
met.
While the use of such clauses is now of long standing usage
in common law jurisdictions, the foreign nature of these
clauses may, in part, explain the difficulty common law courts
have had in dealing with such clauses as is stated in a 1999
article:
The force majeure clause is antithetical to
common law principles. Under force majeure clauses
parties avoid contractual obligations and fault or liability
as ascribed to neither party to the contract, but rather to a
cause beyond the control of either of the parties. Given the
great divergence between common law values and force
majeure clauses, it is not surprising that our courts
have repeatedly shown great reticence in giving effect to
these clauses.13
In the U.S., reference is not made to force majeure
at all, but rather "to impracticability" as arising
from the doctrine of impossibility of performance. The U.S.
approach was described by William Lyman as follows:
The rule, as often quoted, is that absent a contract
provision to the contrary, "[w]here one agrees to do,
for a fixed sum, a thing possible to be performed, he will
not be excused or become entitled to additional compensation,
because unforeseen difficulties are encountered. (Dugan
& Meyers Construction Co., Inc. v. State of Ohio,
162 Ohio App. 3d 491 at 503)14
The doctrine [of impossibility of performance] is invented
by the court in order to supplement the defects of the actual
contract. The parties did not anticipate fully and completely,
if at all, or provide for what actually happened. 'Some
factors determining the applicability of an impracticability
defense include: foreseeability of the contingency, whether the
means of performance will be entirely different than that
agreed to, whether the risk of the contingency was allocated to
a party, and whether the cost of performance will be vastly
increased. It is essentially an equitable defense to the
general rule that an obligor must bear the risk that the
performance of a contract may become more burdensome or less
desirable. Or, said another way in the same decision, the
elements for impossibility of performance were the unexpected
occurrence of an intervening act, such occurrence was of such a
character that its non-occurrence was a basic assumption of the
agreement of the parties, and that occurrence made performance
impracticable.15
Impossibility means not only strict impossibility but
impracticability because of extreme and unreasonable
difficulty, expense, injury or loss involved.
Restatement (First) of Contracts,
§454.16 [and]...
To continue reading
Request your trial