On July 26, 2019, the National Energy Board ("the Board") released its decision concerning the Coastal GasLink Pipeline Project ("CGL Pipeline"). The Board ruled that the CGL Pipeline, including the LNG Export Terminal under development in Kitimat, is a provision work and undertaking and therefore under provincial jurisdiction.

The proceeding before the Board did not address whether the CGL Pipeline should be approved, whether it is in the public interest, or what the environmental, economic, and indigenous impacts are. Instead, the Board was solely focused on assessing whether the CGL Pipeline is a local work or undertaking, which the province of BC should have jurisdiction over, or whether it is part of, or integral to, a larger interprovincial work or undertaking under exclusive federal jurisdiction.

Parties are still considering whether to appeal the ruling to the Federal Court of Appeal.

Implications

The decision comes on the heels of several high profile, energy related division of powers disputes between the provinces and the federal government.1 This decision reaffirms the traditional division of powers principles between the federal and provincial governments. Although a project may have interprovincial implications, such as CGL's ability to export LNG to the Asian market, those implications alone will not create federal jurisdiction.

Background

LNG Canada is a joint venture comprised of Shell, North Montney LNG, Diamond, PetroChina, and Kogas. Together, they proposed to build a LNG Export terminal in Kitimat BC, and a pipeline from Groundbirch, BC, to the terminal. TCPL, a subsidiary of TransCanada Corporation, bid and was successful in the RFP to build the CGL Pipeline.

NOVA Gas Transmission Ltd. ("NGTL") is federally regulated, primarily focusing on moving product to market within Canada and the United States, and is also a subsidiary of TCPL. Further, LNG Canada stated, "a connection may be built between the NGTL System and the CGL Pipeline" (4.2.3). However, there are no current plans for that connection to become a reality.

Due to the connection between these two federally and provincially regulated systems, the Board found that it must consider whether there was functional integration and common management, control, and direction between the CGL Pipeline and the NGTL system such that the CGL Pipeline should be under federal jurisdiction.

Summary of Decision

This decision provides legal clarity on how the Supreme...