Newsletter - Opportunities In Infrastructure In Brazil: Provisional Measure No. 752

After months of discussion, the Brazilian Federal Government published last Friday (November 25) a Provisional Measure ("PM 752") establishing alternative solutions for ongoing concessions. These solutions are basically two: (i) contract term extension followed by a commitment of new investments by the concessionaire (applicable to toll-roads and railways), and (ii) the re-tendering of concession projects - including public private partnerships - PPP (applicable to toll road, railway and airports).

The main innovation brought by PM 752 is the possibility of the contracting public entity and the interested concessionaire agreeing upon the early termination of the concession agreement in force. As a consequence, the project can be re-tendered and granted to a new operator.

Only concession contracts currently under default or whose concessionaires do not have the capacity to comply with contractual obligations are eligible for early termination. Terms and conditions of the termination and of the re-tender process will be regulated on a case-by-case basis.

PM 752 also regulates the conditions under which a concession may have its term extended. The term extension can apply either at the original contractual term or during the life of the original agreement. In both cases, the concessionaire has to comply with certain conditions and request the extension at least 24 months prior to the original expiration date, unless otherwise regulated on a specific...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT