Ninth Circuit Rules That Plans For Dam Operation Do Not Require Annual Environmental Reviews

On August 13, 2012, the Ninth Circuit ruled in Grand Canyon Trust v. U.S. Bureau of Reclamation that the Bureau's preparation of statutorily mandated Annual Operating Plans for the Glen Canyon Dam in Arizona did not trigger the requirements of the National Environmental Policy Act or the Endangered Species Act.

The court held that annual approval of the operating plans for the Dam did not constitute a "major federal action" under NEPA. As a result, yearly environmental reviews were not required and the Bureau's previous programmatic Environmental Impact Statement, completed in 1995, was sufficient for purposes of NEPA compliance. The court similarly found that Congress did not intend for the annual operating plans to be subject to the formal consultation requirement of the ESA. As with its ruling under NEPA, the court found that a programmatic approach was appropriate. This decision is the third Ninth Circuit opinion of the summer touching on what constitutes "agency action" for purposes of triggering ESA consultation. Background

This litigation started in 2007, and due to the importance of the Dam's operations, all seven Colorado River Basin states intervened in the case, as did representatives for water and power users. The plaintiff, the Grand Canyon Trust, claimed that the Bureau – in completing Annual Operating Plans for the Glen Canyon Dam (and other Colorado dams and reservoirs) that were mandated by federal law – was required to complete an annual NEPA review and ESA Section 7 consultation. The Trust also challenged the Biological Opinion prepared by the U.S. Fish & Wildlife Service under the ESA to address the impacts of the Dam's operations on the endangered humpback chub. The district court rejected the first claim, but agreed with the second.

In response, the FWS issued a supplemental Biological Opinion in 2009, but the Trust successfully argued that the Incidental Take Statement associated with the BiOp was not numerically "linked to the take of the protected species." This resulted in a new Incidental Take Statement in 2010, which confirmed that a numeric incidental take limit for juvenile chub could not be established and instead used a surrogate limit based on the number of adult fish. The Trust launched another legal challenge, but this time it lost. The Trust then appealed to the Ninth Circuit, and while the appeal was pending the FWS prepared a new BiOp and Incidental Take Statement in 2011.

The Ninth Circuit's Opinion

...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT