EU Procurement: The 3-Month Rule
It is well known that claims brought for a breach of the 2006
Public Contracts Regulations must be made within a tight 3 month
time limit. There have been two recent cases Brent London
Borough Council v Risk Management Partners Ltd, [2009] EWCA
Civ 490 and Amaryllis v HM Treasury, [2009] EWHC 962 (TCC)
which have considered this principle.
Regulation 47(7) makes it clear that there is a two step
process:
(7) Proceedings under this regulation must not be brought
unless –
the economic operator bringing the proceedings has informed
the contracting authority ... of the breach or apprehended breach
of the duty owed to it.....and of its intention to bring
proceedings under this regulation in respect of it; and
those proceedings are brought promptly and in any event
within 3 months from the date when the grounds for the bringing of
the proceedings first arose unless the court considers that there
is good reason for extending the period within which the
proceedings may be brought.
Brent London Borough Council v Risk Management Partners
Ltd
The Brent case came before the Court of Appeal. Here
RMP claimed that certain contracts of insurance had been awarded by
Brent Authority to the London Mutual Ltd ("LAML") outside
of a tender process in which they participated. It is important to
note that RMP were only making a claim for damages. Amongst other
issues, Brent said that the claims were started more than three
months after the date on which the grounds for bringing the
proceedings first arose. In particular, Brent submitted that
grounds for bringing proceedings existed (and that time therefore
started to run) in November 2006 when RMP were told that Brent was
obtaining insurance elsewhere. Proceedings were not commenced until
6 June 2007. If Brent was right, RMP were well out of time.
Pill LJ noted that:
When considering when grounds for proceedings first arose it
is necessary to bear in mind that the Regulations prescribe the
procedure which a contracting authority must follow before entering
into a contract with a supplier of goods or services... It follows
that a failure by the contracting authority to comply with any step
in the required procedure involves a breach of duty sufficient to
support a claim under the Regulations. Moreover, because the
procedure governs the whole process from the formation of the
intention to procure goods or services to the award of the contract
and is structured in a way that is intended to ensure equal
treatment and transparency throughout, a failure to comply with the
procedure at any stage inevitably undermines the integrity of all
that follows.
In doing so, he expressly recognized the problem that whilst
grounds for bringing proceedings may exist well before the
procedure reaches the award of a contract, the Regulations do not
expressly identify the point at which that will occur. The relevant
chronology was as follows:
On 9 October 2006, Brent resolved in principle to participate
in LAML;
On 7 November 2006, the RMP were told by Brent's brokers
that Brent "had committed to going into the Mutual" but
that there was uncertainty whether it would be ready by the next
renewal date (1 April 2007) and there would be some insurance that
would be sought outside it anyway. Accordingly there was to be a
full tender exercise;
At a meeting on 13 November 2006, Brent resolved to approve
participation in LAML;
In December 2006 Brent invited tenders for cover generally from
1 April 2007;
On 18 January 2007, Brent began membership with LAML;
Because incorrect documentation had...
To continue reading
Request your trial