Contract, Project Abandonment: Separate Legal Concepts
Abandonment is a well-known concept on construction projects
in California. It generally arises in different situations. One
example is when the project's design is so deficient that
the contractor performs a massive amount of change orders and
extra work. This may qualify as contract abandonment, resulting
in the contractor or subcontractor recovering damages against
the owner or prime contractor on a quantum meruit theory (with
the exception set forth below).
Another example is when a contractor wrongfully ceases
working and leaves the project. This is project
abandonment.
Several judicial decisions have established the principle of
contract abandonment, giving rise to its use in construction
litigation. In C. Norman Peterson Co. v. Container Corp. of
America (1985) 172 Cal.App.3d 628, the court held that
when owner imposed changes (or prime contractor imposed changes
vis--vis a subcontractor) are of such a magnitude as to
change the scope of the work originally contemplated, it would
not be fair to limit the prime contractor (or subcontractor) to
the original contract amount. The court pointed out that
"although the contract may be abandoned, the
work is not." Thus, the court noted that contract
abandonment is distinct from project abandonment.
The California Supreme Court's seminal decision,
Amelco v. City of Thousand Oaks (2002) 27 Cal.4th 228,
held that the concept of the owner's contract abandonment
does not apply against a public entity. The court held that
"such a theory is fundamentally inconsistent with the
purpose of the competitive bidding statutes." Further, the
court held that allowing a party in direct privity of contract
with the public entity to throw out the contract and recover on
a quantum meruit theory raised serious public policy
concerns.
Notwithstanding Amelco, a subcontractor on a public
works project is entitled to recover against the general or
prime contractor for contract abandonment. In
Sehulster/Tunnels PreCon v. Traylor Bros. (2003) 111
Cal.App.4th 1328, the court allowed a subcontractor to recover
against the general contractor on a public works project based
on the abandonment theory because the subcontractor and the
general contractor were private contracting parties with a
separate contract. The appellate court cited Amelco as
recognizing the difference between contracts with public
entities (where competitive bidding applies) against contracts
between two private parties (where competitive bidding does...
To continue reading
Request your trial