Proceeding Regularly And Diligently And The 'Hurry-Up' Notice

The recent case of Leander Construction Ltd v Mulalley & Co Ltd [2011] EWHC 3449 (TCC), helps to clarify the law in relation to implied terms requiring a party to proceed regularly and diligently.

The Facts:

In September 2010, Mulalley (the main contractor) engaged Leander (the sub-contractor) to carry out groundworks, drainage, the concrete framework and other associated works at a development known as Tigers Head in Lewisham. By May 2011 it was clear that the sub-contract works were delayed - each party blamed the other. Mulalley served two withholding notices as a result of the alleged delays, claiming that Leander had failed to carry out the sub-contract works in accordance with the programme dates and period set out in the Activity Schedule. Ultimately, Leander commenced proceedings in the Technology and Construction Court.

Mulalley argued that, although the sub-contract did not expressly state so, Leander had an implied obligation to proceed regularly and diligently with the works. It alleged that this implied term must be incorporated into the sub-contract in order to give the sub-contract business efficacy – or in other words, both parties must have intended this term to be part of the contract, as the contract simply would not work without it from a commercial perspective. Leander argued that there was no such implied term.

The Issue:

Did Leander have an implied obligation to proceed regularly and diligently?

The Decision:

Mr Justice Coulson reviewed the relevant test for implying a term into a contract (BP Refinery (Westernport) Pty Limited v shire of Hastings) and held that Mulalley had failed to show that the implied term to proceed regularly and diligently was necessary to give the sub-contract business efficacy. Even though this term had not been included, the sub-contract was adequate and still provided the parties with the sufficient information to evidence the deal that had been agreed. In addition, all previous authorities pointed the same way: 'the courts are very reluctant to imply additional terms as to the timing or regularity of the contractor's performance prior to the contract completion date', particularly where there was already a contractual completion date established in the contract - as there was here.

Commentary:

Mr Justice Coulson's reference back to the 1994 case of West Faulkner Associates v London Borough of Newham will be of interest to contract administrators. In that case, West Faulkner, a firm of...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT