What Developers Need To Know About Limitation Following Grenfell

Published date14 March 2023
Subject MatterLitigation, Mediation & Arbitration, Real Estate and Construction, Trials & Appeals & Compensation, Construction & Planning
Law FirmHerrington Carmichael
AuthorHarriet Greener

The objective of the Building Safety Act 2022 (BSA 2022) was to reform building safety legislation and fire safety. It has become one of the most important pieces of legalisation in the construction industry. Unfortunately, the catalyst was the tragic Grenfell Tower disaster of 2017. As many in the construction industry will be aware, the subsequent review of building regulations and fire safety in 2018, led by Dame Judith Hackitt, found that the current system was not fit for purpose and needed an overhaul.

The BSA 2022 is a long, complex and wide-ranging piece of legislation that finally came into force on 28 June 2022, and the related Regulations being in force from 20 July 2022. Whilst I do not intend to give a comprehensive overview, there are some key points of interest, especially from the perspective of claims being made against developers.

Limitation

A limitation period is the period of time within which a party can bring a claim against another for damages. The Limitation Act 1980 gives the defendant a defence if Court proceedings are issued after expiry of this period.

The BSA 2022 expands the scope of the Defective Premises Act 1972 (DPA 1972) and now allows homeowners to bring statutory claims concerning properties which require refurbishment and rectification works which then renders the property unfit for human habitation. Previously, this was restricted to new dwellings or conversions.

Historically, claims under the DPA 1972 had to be issued within 6 years from the date that the dwelling was completed.

The BSA 2022 radically changes the limitation period and it is now possible for claims to be made up to 15 years from the date of Practical Completion, in relation to buildings completed after 28 June 2022. Developers should be aware that older sites might need to come back into focus.

Even more controversially, there is now a retrospective 30-year limitation period for buildings completed prior to the BSA 2022 coming into force. So, this applies to all properties with Practical Completion between 28 June 1992 to date. Developers and contractors can still be held liable for projects completed in that timeframe. The silver...